Set SW1 (Dip5) CC2 to ON that makes the unit as “Master”, see
picture 19.
(picture 19)
RFID settings for GTB Twinboxes connected in a grid
A maximum of 16 GTB Twinbox may be connected together in a
grid by a shielded twisted pair cable, see picture 20, 21
It is allowed to mix GTB Twinbox with GLB Wallbox in this type of
grid, and the limit is 32pcs “outlets”,
(GTB = 2pcs outlets and GLB = 1pcs outlet).
The first GTB Twinbox in the grid will be the “Master” in the
installation and it is set by SW1 Dip 5 on CC2. All other units in
the grid should be “slaves” set by SW1 Dip 5 on CC2.
First and last GTB Twinbox in the grid should be “end-terminated”
and this is set by SW1 Dip 6 on CC2, see picture 20, 21.
Note: All GTB Twinboxes must be powered on after the physical
installation of the RFID readers during setup of the RFID function
from the “Master”. GTB Twinboxes that are not powered on during
setup will have the RFID function deactivated, and this means they
are available for free use.
RFID settings in the web interface, please see section web
interface in this manual.
RFID settings for stand alone GTB Twinbox
Settings explanation of Dip 5, 6 on SW1 CC2
INSTALLATION OF STANDALONE GTB TWINBOX
(table 4)
SW1
CC2
SW1
CC2
ON
OFF
ON
OFF
MASTER
5
SLAVE
5
SW1
CC2
SW1
CC2
End term
ON
OFF
End term
ON
OFF
OFF
6
ON
6
15
EN