UPS for 208 Vac Grid, B60US-IB Installation Guide, doc. rel. 3.0
23
58. Connect the Ethernet cable. Configures IP address, time server, and DHCP, according to the
preferences of the local IT team. (“Main > Setup > Communications”)
59. Export the log and then clear the log.
3.3.
Installation Procedure
After completing each step in the following installation, return to the Installation Checklist and
place a checkmark or measurement (voltage, current, etc.) next to the corresponding item.
The UPS can come in various unit configuration capacities. The installation
instructions described in this document, extend to the maximum model
configuration capacity.
3.3.1.
Visual Inspection
Perform the visual inspection explained in this section immediately after unpacking UPS.
To perform UPS visual inspection:
1.
Inspect the UPS from all angles and ensure that there is no visible damage to any part
of the cabinet, the module housings, or other coverings.
2.
Verify that the number of modules delivered is as ordered, and that a system controller
module and static switch module are included.
3.
Verify that the LCD display screen is undamaged.
The product you received will include a product inventory list. Confirm contents
included in the UPS crate matches the included product inventory list.
3.3.2.
Physical Site Preparation
Perform the following procedures before connecting any external cables to the UPS.
To perform the physical site preparation procedure:
1.
Ensure that the ambient temperature in the immediate vicinity of the UPS
complies with
system requirements: