background image

If you choose to vary from these instructions your warranty will be impaired

5

5

STEP 5 

DOOR BRACES

The door braces can be fitted now. Tuck one end of the 'Z' between 
the bottom channel of the inside of the door and the sheet in the 
corner. Do the same at the top tucking it behind the door side, the 
two "Z" channels should overlap in the centre behind the padbolt. 
Rivet the 'Z's at the ends where they overlap, and through each "Z" 
into the channel they are tucked under at each end. Two or three 
more fixings will be required through the door sheeting into the 'Z'. 
Drill from the "Z" side but rivet through from the outside of the door 
for a neater appearance.
You may need to cut or bend the flange at the bottom and the top of 
the 'Z' if it catches on the door jamb when opening or closing (see 

AFTER

DIAGRAM 1
BEFORE

YOU WILL NEED

2 x 'Z' Door braces

Fixings

Q

P

NARROW PAN

30MM

4MM GAP 

BETWEEN HINGE 

AND DOOR JAMB

YOU WILL NEED

1 x 1980mm x 715mm sheet for front wall

1980mm 'Z' door jambs without  

channel attached

STEP 6 

HANGING THE DOOR

Rivet the first 'Z' door jamb 

L

 to the 715mm sheet 

B

 on the rib with the narrow pan as 

indicated below. Lay the premade door face down on the 715mm sheet 

B

 approx 30mm 

up from the bottom and down from the top. Check the door is centralised on the sheet 
(top and bottom). Fix the hinges through the side of the 'Z' door jamb 

L

 raising the door 

about 4mm off the 'Z' door jamb. Rivet the second 'Z' door jamb 

L

 to the other 715mm 

sheet 

B

 on the rib with the narrow pan as indicated below. 

B

L

B

L

Summary of Contents for GVO 3023

Page 1: ...riveter Tape measure Ladder Non slip gloves good shoes and goggles A set of helping hands CALL 0508 454 873 for an installer near you Some parts have sharp edges and should be handled very carefully W...

Page 2: ...M Q B F J N R S C G K O D L P ASSEMBLY OVERVIEW These instructions are designed to guide you though the process of building your new garden shed It is a simple process of joining sheets together befo...

Page 3: ...t every second rib but not the corners at this stage Place the short flange of the first L flashing M on top of the rib at one end Make sure the ends are flush with the sheeting diagram 1 and put one...

Page 4: ...age for 2nd door Attach 1770mm Z door jamb to 2nd door onto the on the same side as the door plate This Z serves as a weather flashing between the doors when they are closed 150MM A J L O P N J L P L...

Page 5: ...may need to cut or bend the flange at the bottom and the top of the Z if it catches on the door jamb when opening or closing see AFTER DIAGRAM 1 BEFORE YOU WILL NEED 2 x Z Door braces Fixings Q P NARR...

Page 6: ...ts with the 3000mm channels F Use the door spacers K to make sure the door fits the gap they sit on top of the Z door jambs N see diagram 1 Drill and fix rivet or screw the channels at every second ri...

Page 7: ...he pan into the top channel of the front and the back walls 10mm more than the overhang Fix beside every second rib You will not need to worry about these fixings leaking as any water seeping through...

Page 8: ...nt or act of God including weather b The warranty shall cease and the Supplier shall thereafter in no circumstances be liable under the terms of the warranty if the workmanship is repaired altered or...