MAINTENANCE

 

FBW-IOM-2014-0311 

SECTION 4

4-2

 

!

WARNING

All information in this manual is for 
reference and guidance purposes, 
and does not substitute for required 
professional training, conduct, 
and strict adherence to applicable 
jurisdictional/professional codes and 
regulations. 

Prior to any maintenance concerning 
electrical components of this 
equipment,  ensure electrical supply 
to the equipment is disconnected.  
Label all wires prior to disconnection; 
wiring errors may cause improper 
and hazardous operation.

Follow all proper lockout/tagout 
procedures for service. 

Before beginning any maintenance, 
ensure area is free of any combustible 
materials and other dangers. 

Do not use harsh cleaning 
compounds that could damage this 
equipment.

 

4

CAUTION

All maintenance procedures should 
be completed by trained personnel. 
Appropriate training and instructions 
are available from the  Fulton Service 
Department at (315) 298-5121 or your 
local Fulton Thermal Representative.

In order to meet warranty conditions, 
ensure  all appropriate maintenance 
activities are performed. 

General

Your boiler has been designed to provide years of trouble free performance. 
To ensure continued safety and effi

  ciency of the boiler, please follow the 

maintenance and inspection directions outlined in this section of the manual. 

Daily Maintenance and Inspection Schedule 

Daily maintenance and inspection must include the following:

1.  Check all valves for proper opening and closing. 

2.  Check supply water pump for proper operation.

3.  Check make-up air water meter reading to verify no excessive leakage from 

hot water loop has occurred. 

Monthly Maintenance and Inspection Schedule

Monthly maintenance and inspection must include the following:

1.  Check safety valve for proper operation.

2.  Check low-water cut-off  relay for proper operation.

Annual Maintenance and Inspection Schedule

Annual maintenance and inspection must include the following:

1.  Inspect bottom of boiler for scale and lime by removing heating element. 

Clean/replace as needed. It is critical to perform this when boiler is cool 
and is vented to the atmosphere. 

2.  When the water level drops, the low water relay will shut off  the contactor.  

This shows that the relay is working properly. 

3.  Check for loose terminals and wiring connections. 

4.  Remove and clean the water electrode probe in the boiler. 

5.  Inspect boiler shell for possible mineral build-ups and clean if necessary. 

6.  Inspect elements on top of boiler for leaks, or loose fl ange bolts and nuts. 

7.  Check elements for correct amp rating. 

8.  Provide annual inspection by qualifi ed ASME boiler inspector. 

9. See 

Handhole Gasket Installation section

 for correct hand hole gasket 

installation.

10.  Check temperature/pressure gauge periodically to verify compatibility 

with the operating aquastat/controller. 

Summary of Contents for FB-W 012

Page 1: ...INSTALLATIONAND OPERATIONMANUAL Electric HotWater Boiler FB W 12 to 700 kW 1 2 to 70 HP Serial National Board Model Fulton Order SoldTo Job Name Date FBW IOM 2014 0312...

Page 2: ......

Page 3: ...Control 2 5 STEPCONTROLLERS 2 5 WaterSupply 2 5 WATERQUALITY 2 5 WATERSPECIFICATION 2 5 ElectricalInstallation 2 7 MOTORS 2 7 ELECTRICELEMENTS 2 8 Operation 3 1 BeforeStartUp 3 2 Start Up 3 2 BoilerCo...

Page 4: ...TheFultonCompanies2014 TABLEOFCONTENTS FBW IOM 2014 0311 0 2...

Page 5: ...Questions Call 315 298 5121 orvisitusonlineat www fulton com 1 1 INTRODUCTION INTRODUCTION 1 INSTALLATION 2 OPERATION 3 MAINTENANCE 4 WARRANTY PARTS 5...

Page 6: ...otes in literature on stickers and labels and any additional safety precautions that apply Follow all safety codes and wear appropriate safety protection Follow all jurisdictional codes and consult an...

Page 7: ...Questions Call 315 298 5121 orvisitusonlineat www fulton com 2 1 INSTALLATION INTRODUCTION 1 INSTALLATION 2 OPERATION 3 MAINTENANCE 4 WARRANTY PARTS 5...

Page 8: ...h element This results in low flux temperatures and long element life Multiple vertically oriented stainless steel or Incolloy elements discourage build up because element expansion and contraction ca...

Page 9: ...UL requires at least 36 clear space be maintained in front of any electrical panel 3 Ensure all labels on the boiler will be fully visible for maintenance and inspection BoilerTrim Each boiler is sup...

Page 10: ...0 20 20 20 20 20 17 17 24 24 28 28 36 40 40 44 44 50 50 MM 508 508 508 508 508 508 432 432 610 610 711 711 914 1016 1016 1118 1118 1270 1270 H Overall Depth Electric Panel to Drain IN 34 34 34 34 34 3...

Page 11: ...s and dissolved minerals These materials may promote corrosion deposition and or fouling of equipment To prevent TABLE 1B SPECIFICATIONS Model FB W 012 015 018 024 030 036 050 070 105 140 175 210 280...

Page 12: ...per less than 25 ppm Corrosion Inhibitor level capable of maintaining iron corrosion rates 2 mpy Due to changing environmental restrictions a non heavy metal all organic inhibitor is recommended which...

Page 13: ...ect wiring as shown in wiring diagram which is furnished inside the electrical control panel Be sure to install a fused switch for the contactors and a separate fused switch for the circulating pump s...

Page 14: ...c elements will have an increase in watt density if the applied voltage is higher than the element design voltage Therefore electric elements have a 0 tolerance for operation over design voltage Elect...

Page 15: ...Questions Call 315 298 5121 orvisitusonlineat www fulton com 3 1 OPERATION INTRODUCTION 1 INSTALLATION 2 OPERATION 3 MAINTENANCE 4 WARRANTY PARTS 5...

Page 16: ...ter level is too low A low water cut off condition will require pushing the manual reset button on the panel box Water Relief Valve ASME Approved releases extra pressure Water Outlet Valve allows wate...

Page 17: ...he fused switch that controls the circulating pump should be kept in the on position at all times during the boiler operation as well as during the non operating period of the boiler This should be tu...

Page 18: ...conduct and strict adherence to applicable jurisdictional professional codes and regulations Failure to follow instructions may result in a fire or explosion causing property damage personal injury o...

Page 19: ...Questions Call 315 298 5121 orvisitusonlineat www fulton com 4 1 MAINTENANCE INTRODUCTION 1 INSTALLATION 2 OPERATION 3 MAINTENANCE 4 WARRANTY PARTS 5...

Page 20: ...section of the manual DailyMaintenanceandInspectionSchedule Daily maintenance and inspection must include the following 1 Check all valves for proper opening and closing 2 Check supply water pump for...

Page 21: ...oroughly clean the surface on boiler and on plate 2 Place neoprene gasket on handhole plate Be sure the gasket is pushed down tight on the plate Do not use any grease lubricant or adhesive 3 After pla...

Page 22: ...verify power in each stage or that component is supplied 2 If part of the voltage is stopped at any point replace that component and continue the test until all circuits test clear Control Switch Fail...

Page 23: ...ff an ohm meter can be used to check the contactor points between the contac tor supply and contactor feed to verify the contactor is pulling in A visual inspection on the side of the contactor can be...

Page 24: ...TheFultonCompanies2014 MAINTENANCE FBW IOM 2014 0311 SECTION4 4 6...

Page 25: ...Questions Call 315 298 5121 orvisitusonlineat www fulton com 5 1 WARRANTY PARTS INTRODUCTION 1 INSTALLATION 2 OPERATION 3 MAINTENANCE 4 WARRANTY PARTS 5...

Page 26: ...lly completed and returned the equipment Installation and Operation Checklists to Fulton s Quality Assurance department General Fulton shall be notified in writing as soon as any defect becomes appare...

Page 27: ...nd system performance and voids the product warranty Parts Spare and replacement parts may be ordered from your local representative or through the Fulton Companies When ordering replacement parts ple...

Page 28: ...TheFultonCompanies2014 WARRANTY PARTS FBW IOM 2014 0311 SECTION5 5 4 THIS PAGE INTENTIONALLY LEFT BLANK...

Page 29: ...Questions Call 315 298 5121 orvisitusonlineat www fulton com SECTION5 FBW IOM 2014 0311 WARRANTY PARTS 5 5 THIS PAGE INTENTIONALLY LEFT BLANK...

Page 30: ...TheFultonCompanies2014 WARRANTY PARTS FBW IOM 2014 0311 SECTION5 5 6...

Page 31: ......

Page 32: ...nstallation Operation and Maintenance manual may be reproduced in any form or by any means without permission in writing from the Fulton Companies Fulton BoilerWorks Inc Fulton Heating Solutions Inc F...

Reviews: