28
Performing the Resistance Test
The Resistance Test screen allows you to run an internal resistance test on all sensors. You must
complete this test at commissioning.
1. Choose Resistance Test on the web Interface landing page Menu tab.
2. Select the string to be tested, and click Test IR. During the test, each sensor light turns red.
3. Enter “7” in the days field to perform the IR Test every 7 days.
Confirming IR values
1. Choose Monitoring Data on the web Interface landing page Menu tab to see Resistance Test
results.
2. Click Next Page to see data for the first 20 batteries. Click Next Page again to see the
remaining batteries in the target string.
3. Use the Target String numberdrop-down list to choose additional strings.