EMG 1500 Operating Manual
Commissioning
9
4. Commissioning
4.1 Preparations before commissioning
Caution:
It must be ensured that the instrument terminals can no longer
be touched before the instrument is commissioned. This can
be by means of a closed cabinet door, a protective hood or
similar.
Once the installation has been completed as in Section 3 and the
above safety notice has been complied with, the EMG 1500-PN can
be powered up and commissioned.
4.2 Instrument self-test
The Run LED comes on when the power supply to the instrument
has been switched on. After about 20 seconds the EMG 1500-PN is
ready to operate and the Run LED begins to flash once per second.
4.3 Assigning an IP address
The EMG 1500-PN requires a unique IP address before it can be
accessed via the Ethernet. The address is assigned using the
software “EMG-SW” supplied as part of the package together with
the “FRAKO-NET” software or supplied on request.
This software enables the user to
assign
the
EMG
1500
an
IP address, a subnet mask and a
gateway address. To do this,
however there must be a serial
connection
between
the
EMG
1500-PN
and
the
PC
(see also Section 3.2.4, page 8)
The assignment of a gateway
address is optional. If this entry field
is cleared, no gateway address is
assigned to the EMG 1500-PN.
Clicking
the
Write
settings
transfers the data to the EMG 1500-PN where they are saved in
non-volatile memory. The instrument must then be restarted for the
new settings to become effective (switch AC power supply off and
on again).