Install with P-installation
In the P-installation, the pump is installed on a stationary discharge connection, and
operates either completely or partially submerged in the pumped liquid. These
requirements and instructions only apply when the installation is made according to the
dimensional drawing.
WS006259A
Figure 2: P-installation
These items are required:
• Guide bars
• Guide bar bracket for attaching the guide equipment to the access frame or to the
upper part of the sump
• Cable holder for holding the cable
• Access frame (with covers) to which the upper guide bar bracket and cable holder can
be attached
• Discharge connection for connecting the pump to the discharge line
The discharge connection has a flange which fits the pump housing flange and a
bracket for attaching the guide equipment.
• Fasteners for the discharge connection
• Anchor bolts
1. Install the access frame:
a) Place the access frame in position and align it horizontally.
b) Grout the frame in place.
2. Grout the anchor bolts in place.
Be careful when you align and position the discharge connection in relation to the
access frame.
3. Place the discharge connection in position, and tighten the nuts.
4. Install the guide bars:
a) Secure the guide bars in the bracket.
b) Check that the guide bars are placed vertically. Use a level or a plumb line.
5. Connect the discharge pipe to the discharge connection.
6. Lower the pump along the guide bars.
When it reaches the bottom position, the pump automatically connects to the
discharge connection.
7. Secure the motor cable:
Installation
18
Flygt 3126.290 Installation, Operation, and Maintenance Manual
Summary of Contents for 3126.290
Page 1: ...Installation Operation and Maintenance Manual Flygt 3126 290 ...
Page 2: ......
Page 47: ......