Kompact AG Installation—November 2018 8
1
Carefully remove all packaging.
2
The firebox front when installed must be flush with the finished fireplace surround
and on a level base of the same height as the finished floor protector. This may be
achieved by using a concrete mix to level the base.
3
Slide the firebox into the opening so that the outer casing return folds are flush with
the finished fireplace surround.
4
It is important to anchor the fire box down in case of movement. Restraint points
are provided through the fires two front legs.
5
Install Flue as per instructions on page 11
-
13.
6
Now that the firebox and flue are in position,
place 25mm white Kaowool
blanket
(supplied) on top of casing
.
7
As this fire sources its combustion air from the chimney cavity/enclosure,
the Fire
MUST be sealed around the front between the casing and the masonry. This
is achieved by packing the yellow ISB insulation supplied between the
casing and the masonry at the FRONT ONLY to maximum depth of 80mm. As
shown on pages 9 and 10.
8
Assemble and fit the fascia as per instructions on the relevant pages 27
-
37.
NOTE:
In the case of some insert fires into existing masonry fireplaces it may be
necessary to install additional ventilation into the chimney cavity as per
AS/NZ 2918 3.4.1.2 to assist air flow into the fire. This ventilation should not
be taken/drawn from the room that the fire is installed in.
5. ASSEMBLY INSTRUCTIONS
Summary of Contents for Kompact AG Series
Page 9: ...Kompact AG Installation November 2018 9 6 TYPICAL INSULATION REQUIREMENTS ...
Page 15: ...Kompact AG Installation November 2018 15 ZERO CLEARANCE BOX Built in Fire Canopy ...
Page 18: ...Kompact AG Installation November 2018 18 ZERO CLEARANCE BOX Built in Fire Canopy ...
Page 19: ...Kompact AG Installation November 2018 19 ZERO CLEARANCE BOX Built in Fire Canopy ...
Page 20: ...Kompact AG Installation November 2018 20 ZERO CLEARANCE BOX Built in Fire Canopy ...
Page 21: ...Kompact AG Installation November 2018 21 ZERO CLEARANCE BOX Built in Fire Canopy ...
Page 22: ...Kompact AG Installation November 2018 22 ZERO CLEARANCE BOX Built in Fire Canopy ...
Page 27: ...Kompact AG Installation November 2018 27 14 KOMPACT WITH ATHENA FASCIA ...
Page 29: ...Kompact AG Installation November 2018 29 KOMPACT WITH DECO FASCIA ...
Page 33: ...Kompact AG Installation November 2018 33 KOMPACT WITH FORTE FASCIA ...