6
7. Assembly Instruction
ATTENTION –
A
To avoid risks of electrical shock, all installation and
wiring operations must be carried out with the DC disconnect switch
internal and external (if present, applying LOTO procedures on it)
to OFF position and with the external AC disconnect switch to OFF
position (applying LOTO procedures on it).
ATTENTION –
A
During installation, do not place the equipment with
its front facing towards the ground.
READ THE MANUAL –
E
The underlying procedure is related to the
side-by-side installation of REACT2-BATT. Alternatively, is possible to
install the REACT2-BATT separately and at greater distances using
the “REACT2-XL-CABLE-KIT” cable kit (2 meter cables length).
• Position the REACT2-BATT bracket
(20)
so that it is perfectly level on the
wall and use it as a drilling template. To aling the two brackets use the
reference point and follow the steps as in the picture.
• It is the installer’s responsibility to choose an appropriate type of screw
anchors for the attachment points. The choice must be based on the type
of support (wall, frame or other support), the type of anchors to be used,
and their ability to support 4 times the inverter’s weight (4x50Kg=200Kg).
Depending on the type of anchor chosen, drill the required 2 holes
B
to
mount the bracket.
• Install the REACT2-BATT bracket
(20)
to the support.
01
20
B
B
2 x
Ø
9 mm
STEP 1
STEP 2
• Lift the REACT2-BATT up to the bracket and insert the heads of two
anchor points (present on the back of the battery unit) into the slots
on the bracket
(20)
.
LIFTING –
U
Risk of injury due to the heavy weight of the equipment.
• Hang up the lower part of the REACT2-BATT to the wall using the two wall
attachment point
(26)
(holes diameter 11 mm).
• Remove the caps from the battery and inverter connectors (if present).
- To remove the battery signal connectors
(08)
simply pull it.
- To remove the battery power connectors
(09)
press the latch (highlighted
in red) and pull it off.
DC SWITCH
COM.
GRID
+/ -
COMM.
[B]
POWER
[B]
COMM.
[A]
POWER
[A]
08
09
09
08
• Connect the two battery cables between inverter and battery unit
(supplied inside the REACT2-UNO box).
• Give each cable a pull test to confirm the connection is secure.
Click
Click
Click
COMM.
[B]
POWER
[B]
COMM.
[A]
POWER
[A]
Click
COMM.
[B]
POWER
[B]
COMM.
[A]
POWER
[A]
Click
Click
To execute all external grounding connection, follow the procedure
described below:
1. Make a jumper earth cable using the two cable lugs supplied (minimum
cross-section not less than 4mm²). The cable must be long enough to
connect the REACT2-UNO external protective earth
(11)
to the REACT2-
BATT external protective earth [A]
(25)
.
2. From among the components supplied, find the M5 nut, M5 flat washer
and M5 serrated lock washer.