TST
Assembly instructions
FUF2 / FU3F-A/-C/-F
FEIG ELECTRONIC GmbH
Page 71 of 114
TST_FUxF-A-C-F_Montageanleitung_EN_15
U1
V1
W1
W2
U2
V2
L1
L2
L3
U1
V1
W1
W2
U2
V2
L1
L2
L3
Star wiring
Delta wiring
Figure 43: Star/Delta wiring
The automatic query of basic data can be interrupted by pressing the
OPEN
button when the controller is being turned ON. This causes a direct jump to the
parameter configuration mode.
9
Commissioning
Before starting the controller, check the electrical connections and the correct installation
of the plug-in cards.
After commissioning, the operation of all the safety devices must be checked.
The settings are performed in dead man mode, i.e. press and hold the corresponding
arrow key in the corresponding direction until the desired position is reached.