SECTION 2 - ASSEMBLY and COMMISSIONING

 

2.1 ASSEMBLY

 

The  appliance  is  supplied  complete  and  ready  to  be  connected to the mains supply.

 

Position  unit  in  desired  location  and  level  it.  Turn  lower  section  of  each  leg  clockwise  to  raise  corresponding 

corner height or anti-clockwise to lower it.

 

  

Castors

 

Undo grub screw and use a spanner to adjust the castor  height. Turn clockwise to raise level and anti-clockwise  to 

lower.

 

Secure grub screw when task is completed.

 

 
 
 

 
 
 

 

 

Grub screw

 

 

 
 

 

 

 

 

2.2 CONNECTION TO THE ELECTRICAL SUPPLY

 

To gain access to terminals, proceed as follows:-

 

Remove fixings at unit rear to remove cover and access  electrical connections.

 

Undo cable gland.

 

Feed cable through cable gland into electrical box.  Connect leads to respective terminals.

 

Tighten cable gland.  Replace cover.

 

If single phase connection is required, refer to Section 1.3  for details.

 

 

2.3 COMMISSIONING

 

Fill   pan(s)   with   oil   to   mark    on    element    guard 

(i.e. approximately 20 litres for E3830 model and 40 litres  for 

E3860 & E3865 models) 

and switch on at  isolator  switch.  Turn  thermostat  to  maximum  setting  and  check  that 

it  operates at the correct temperature of 190°C. 

 

The  importance  of  never  switching  on  the  elements  unless 

they are covered by oil or water must be stressed.  DO NOT USE 

SOLID FAT. 

 

 

2.4 INSTRUCTION TO USER

 

After installing and commissioning appliance, hand user  instructions to user or purchaser.

 

Ensure that person

(s) 

responsible is 

(are) 

made familiar  with use and maintenance of unit. 

 

 

Summary of Contents for DOMINATOR PLUS Series

Page 1: ...of the operation and cleaning of the appliance IT IS MOST IMPORTANT THAT THESE INSTRUCTIONS BE CONSULTED BEFORE INSTALLING AND COMMISSIONING THIS APPLIANCE FAILURE TO COMPLY WITH THE SPECIFIED PROCEDU...

Page 2: ...s Poor combustion caused by lack of cleaning Lubrication of moving parts Lubrication of gas cocks Cleaning adjustment of pilots Correction of gas pressure to appliance Renewing of electric cable ends...

Page 3: ...CTION The unit is designed for use on AC supplies only and terminals are normally arranged for either 2 phase operation E3830 model or 3 phase E3860 E3865 models If single phase supply has been specif...

Page 4: ...ections Undo cable gland Feed cable through cable gland into electrical box Connect leads to respective terminals Tighten cable gland Replace cover If single phase connection is required refer to Sect...

Page 5: ...having rectified the fault it is necessary to press the re set button This is situated within the turret which projects through element box rear The oil must be allowed to cool to enable safety therm...

Page 6: ...y dry pan and all fittings before re filling with oil The elements can be lifted and hinged backward to gain full access to all surfaces of pan and elements 3 7 TILT SWITCH Located in element terminal...

Page 7: ...E3830 WIRING DIAGRAM...

Page 8: ...E3830 CIRCUIT DIAGRAM...

Page 9: ...E3860 WIRING DIAGRAM...

Page 10: ...E3860 CIRCUIT DIAGRAM...

Page 11: ...E3865 WIRING DIAGRAM...

Page 12: ...E3865 CIRCUIT DIAGRAM...

Reviews: