FIXING THE ANCHORING BASE PLATE OF FIBO 300 AND FIBO 400
Before fixing the operator base plate, it is advisable that a tube be laid under the ground from an accessible junction pit (to be
provided nearby) through the Ø 50 hole into the base plate (Pic. 8). Fit the four expanding bolts (not included with the equipment)
into the holes in the foundation as previously drilled, in respect of the distance between the holes in the base plate, while depth
is to follow the rules of good installation technique and soil nature (Pic. 7).
MANUAL RELEASING FIBO 300 AND FIBO 400
In order to properly install the gear rack all along the gate, it is first necessary to disengage the gate from the Fibo 300 or Fibo 400
motors, once these have been installed. Overriding for manual operations is by the spanner supplied with the equipment and the
release system is positioned in the front side of Fibo 300 or Fibo 400 on the drive gear shaft: unlock the M18 (for Fibo 300) or M22
(for Fibo 400) nuts by a few turns to release.
!
IMPORTANT: Make sure Fibo 300 or Fibo 400 be perfectly aligned by means of a spirit level (Pic. 8), then tighten
the four nuts and washers to the four bolts.
INSERTING AND FASTENING THE BOLTS
M16
Ø 16
70 mm
After drilling the 4 holes, making sure distances are
correct, insert the bolts and let them protrude 70 mm
70 mm
Tighten the nut very hard and let
the bolt protrude 70 mm
1
2
M16 anchoring
bolts into the
foundation or
pavement
Spirit level
Junction pit
Fibo 300 -
65 mm
Fibo 400 -
80 mm
Corrugated tube to be laid
under the ground for cable
leading
Tighten the four nuts and washers
very hard
Base plate
Spirit
level
Fibo 300
M18 self locking nut
UNLOCK TO
RELEASE
LOCK
Release box spanner
E 23-27
Fibo 400
M22 self locking nut
UNLOCK TO
RELEASE
LOCK
Release box spanner
E 30-32