EVAPCO ESW4 Rigging And Assembly Instructions Download Page 14

14

ESW4 Closed Circuit Coolers

General Information - Start-up & Maintenance Start-up Details 

Shipping Chocks and Debris

Remove any chocks that have been placed inside the unit for shipping purposes. Be sure to remove the chocks from between the

fan and fan guard if applicable. Clean all debris from the basin prior to start-up. Clean and secure all access doors.

Pump Discharge Line

Connect the riser pipe from the pump discharge on the basin section to the riser pipe on the coil/fan section using the flexible

connection and hose clamps provided.

Bleed-off Line

A bleed-off line and valve are installed on the unit when shipped with a pump. On units shipped without a pump (remote sump

applications) make sure a bleed-off line and valve are properly sized and installed on the discharge side of the pump and

connected to a convenient drain. In either case, the bleed-off valve should be fully open.

Strainer

Check the strainers, if applicable, in the basin section to make

certain they are in the proper location over the pump suction,

along side of the anti-vortex hood. (See Figure 24.)

Screens

Protective fan screens are provided across the top of the fan cylinders of all models. Check and tighten all bolts.

Float Valve Adjustment

The float valve is pre-set at the factory; however, adjustment

should be checked after rigging. The float valve should be

adjusted so that the centerline of the float is at the

measurement shown in Table 6 from the basin bottom. Raise

or lower the float by using the wing nuts on the vertical

threaded rod only. Do not adjust the horizontal rod.

SUCTION HOOD

STRAINER

Figure 24 

– Strainer Location

Unit Width

Level

8.5’ (2.6m)

9” (23cm)

12’ (3.6m)

10” (30cm)

14’ (4.2m)

9” (23cm)

Table 6 

– Recommended Water Level

Summary of Contents for ESW4

Page 1: ...Bryan TX USA 979 778 0095 p rvs rvscorp com EvapTech Inc A wholly owned subsidiary of EVAPCO Inc Edwardsville KS USA 913 322 5165 p marketing evaptech com Tower Components Inc A wholly owned subsidiar...

Page 2: ...electrical connections These items must be flexibly attached to the Evapco unit so as not to transmit additional loads to the equipment as a result of seismic or wind forces Structural Steel Support E...

Page 3: ...e strain on the lifting devices See Table 2 for the minimum H dimension Bolt the bottom section to the steel support before rigging the top section of the unit The unit lifting devices should not be u...

Page 4: ...the supporting steel and bolted in place the top flanges should be wiped down to remove any dirt or moisture Sealer tape should be placed over the mounting hole centerline on the side flanges along th...

Page 5: ...r exists and for final positioning of the section For extended lifts safety slings should be provided under the section as described on page 6 2 OVERLAPPING LAYERS OF SEALER TAPE ON THE ENDS 1 LAYER O...

Page 6: ...s to assure proper alignment lower the top section down onto the bottom section Place nuts and bolts in all four corner bolt holes Then continue to install the rest of the nuts and bolts working from...

Page 7: ...section separate from the casing section the center of gravity of the fan section is heavily biased towards the location of the fan motor and major drive components In order to avoid lifting the fan...

Page 8: ...match markings on each section i e A1 of bottom section should match up with A1 of top section Lower the upper section to within several inches of the bottom section making sure the two sections do no...

Page 9: ...s supported from underneath by an X shaped support frame Set the support frame across the top of the discharge cylinder See Figure 13 and fasten to cylinder with 3 8 10mm bolts 3 Place the fan screen...

Page 10: ...it for belt installation 7 Install Powerband belt K Figure 15 around fan sheave and motor sheave Tighten belt by adjusting nuts on J bolts Do not over tighten the belts The center of the belt should d...

Page 11: ...a heater a low water cutout switch and a thermostat The heater is installed at the factory The low water cutout switch is shipped loose in the rigging box and will need to be screwed into the screw ti...

Page 12: ...ing bolts A from the ladder mounting channels B on pan and casing sections 2 Loosen but do not remove the ladder bracket and assembly bolts C 3 Slide the ladder bracket assembly D over the ladder moun...

Page 13: ...9 6 216 3 57 1 7 6 1 2 66 0 0 7 12 0 7 5 127 9 3 2 1 7 21 17 7KLV GRFXPHQW LV WKH SURSHUW RI YDSFR QF W VKRXOG QRW EH FRSLHG RU GLVFORVHG ZLWKRXW SULRU ZULWWHQ DXWKRUL DWLRQ 6 127 6 3 7 250 5 7 1 127...

Page 14: ...installed on the discharge side of the pump and connected to a convenient drain In either case the bleed off valve should be fully open Strainer Check the strainers if applicable in the basin section...

Page 15: ...tional arrows are placed on the side of the fan cylinder Maintenance Once the installation is complete and the unit is turned on it is important that it be properly maintained Maintenance is not diffi...

Page 16: ...Water Level Control Probes Mounted in PVC standpipe Electronic Water Level Control PVC Standpipe Strapped Inside Unit Basin Shipping Location is Unit and Accessory Dependent External Service Platform...

Reviews: