EXP120K1-HT 120KW DC Charger
Cap. 2 - Instalation
2.1
Safety rules
As the working voltage and current inside the system is very high, the following rules must be taken into account
to ensure your personal safety:
1 – Only qualified tchnicians who have EV charging training can install the system. During the installation always
observe the safety precautions mentioned in this document and all National Safety Standards.
2 – Make sure that the DC output of the charging system is switched off for operation inside the charger system.
The main input of the charging system must be also be off.
2.2
Installation preparation
•
Unpack the equipment for inspection.
When the equipment arrives at the installation site, the packaging should be opened for inspection. During the
inspection open the packaging and with the list of items, check one by one to make sure the equipment is complete.
Then check the equipment serial number, packaging, quantity, acessory types to sure they are compliance.
•
Cable preparation.
Cable selection must be in accordance with national regulations. We recommend using RVVZ type cables as AC
cables with the rated voltage of 550 / 750 Vac or higher and a minimum temperature of 70ºC. Technicians / users
determine a sectional area of the charger input and output cables according to table 2-1
Table 2-1 Cable section selection of charging integrated cabinet
Connector name
Allowable
maximum
current
Minimim
sectional
area
Maximum voltage
drop leght <0.5V with
minimum sectional
area
Maximum
sectional area
Maximum leght <0.5V
voltage drop and
maximum sectional
area
Carregador
armário DC com
entrada AC
233A
70mm
2
5m
95mm
2
10m
Note: When the wiring distance is less than 30 meters, it is recommended to estimate the sectional area of the
used line according to a current density of 2,5A / mm
2
.
The ground cable cross-section should be consistent with the most power distribution cables, but not less than
35mm
2
. The screw on the ground bus is the M8.
Note:
It is not usual to use a separate ground wire. Normally 5W standard cables (3Ph + N + PE) are used as
show in picture 2.3. the diagram on page 25 should be updated to be in line with the arrangement of the AC input
terminal.
EV Vision – Porto – Portugal –
www.ev-vision.com
– Support service: (+351) 229 999 230
All rights reserved. This manual may be changed without prior notice. - V 1.0 – 2019/08/10 – Pag. 10 de 25