# VSH400PLC090909
- 5 -
conductors
GU 625
Head for clamping terminals on cables 300 – 625 mm2
GW
Head for punching holes in switching cabinets
GC 50N
Head for cutting cable conductors
GC 100
Head for cutting cable conductors
GL 6
Assembly rail cutter
GLP
Assembly rail cutter
4.
MACHINE INSTALLATION
The station should be positioned on hard and even foundation, so that it will
securely lean on all four wheels.
Operation of the station on an unadapted foundation may result in
accelerated wear and in some cases it can be a cause of a defect or
destruction of the station.
Block the brakes of the station wheels.
Connect the equipment to the electrical power supply.
In order to work properly, station type SH400PLC requires five-line electrical
network - L1, L2, L3, N, PE in any sequence of phases. For four-line network it is
necessary to bridge PE and N lines in the supply socket.
5.
CONTROL PANEL
The control panel consists of the following elements:
The main switch Q1 – used for starting the station.
A white signalling lamp L1 – used for signalling correct power supply.
LCD panel with a touch screen – contains technological software.
Emergency stop switch Q2.
Foot switch Q3 – acts as an operational switch-key.
Body height regulating crank S1.
Limiter stop S2.
Fig. 1.
crank