Operating Instruction
Spindle lifting system SLA/SLG VD
Document no.: B-00081
Edition 2019 02
Operating instruction EN
Copyright by Ergoswiss AG
12/20
4
Initial operation
ATTENTION
Before commissioning the lifting system, the entire system must be assembled correctly ac-
cording to the assembly instruction. Commissioning is prohibited until the entire system
complies with the provisions of EG Machinery Directives 2006/42/EG. For this, a risk analysis
of the complete system must be carried out so that you can react to possible residual dan-
gers (for example by constructive measures or by instructions in the operating instructions
and/or by safety instructions on the system.)
ATTENTION
While using the height adjustment of the work surface there is a danger of squeezing. It is
important to make sure that no objects or people are within the danger area and no one is
reaching into the danger zone.
ATTENTION
The lowest block position must always be reachable. The lifting element is not allowed to hit
a stop before it reached its lowest block position. Otherwise the reference will be stored at a
wrong height.
NOTE
During the initial operation the control box works with only half power and half speed. The
system should be fully loaded after finishing the initial operation.
1.
Keep the buttons
and
pressed simultaneously to drive to the under block position.
The system moves downwards at half speed. Upward movement is disabled.
2.
After reaching the block position, let go of the buttons
and
.
The control box will give a click-sound and the system will drive out a few millimeters.
After reaching the block position, the lower and the upper position will be stored automatically. The initial
operation is completed.
(The lower position is 3 to 4 mm higher than the block position. The upper position depends of the lifting
element type, resp. of the control box software.)