HA8-LP Manual V. 4.0
Pull Header
Ensure before fastening Header box to the door frame that your holes for high and low voltage wires match. Header box
should be referenced to the hinge side of the door and 1
3/8” above the bottom of the door frame (see figure below).
For most applications, the header is equal to the door opening plus 3”.
This allows for a 1.5” space on either side of the Header Box to anchor the Header box properly to the frame.
For correct sized header,
the header box should be anchored with a minimum of (6) six #14 x 1” Pan Quad Type A screws
(provided), but will also depends on what is being screwed into.
•
The locations of the screws on the header will be application dependent.
•
Fasten the header body as application requires. The header must
support 200lbs.
•
Do Not use Drywall Screws or Hollow Wall Anchors to mount the
back plate / header.
•
Header on pull applications must be mounted so the main drive
pinion safety washer and machine screw are above the top of the
door. This is to ensure the spindle does not obstruct the swing path
of the door.
•
For application with Universal arm, header will be installed differently.
See section 3.4.
2.3
Handing Modification - Left to Right (and vice versa)
Prepare the Operator, Arm and Spindle
1
Invert the entire operator assembly 180 degrees
2
Remove drive shaft (spindle) from motor gear box assembly (See changing position of drive shaft)
3
Re-attach drive shaft (spindle) to opposite side of motor gearbox assembly
4
Detach wire connections from operator to control board
5
Remove control assembly from the base and rotate 180 degrees
6
Replace control and socket screws
7
Connect wire harness (see wiring)
8
Fully tighten all bolts
9
Insert spline shaft on the operator (depended on push or pull application and spindle rotation)
2.0 OPERATOR INSTALLATION
1 3/8in [34.23mm]
Filler