Prepare the AC Combiner Box

A )  If needed, reposition the mounting feet. You can adjust each of the 

four mounting feet to several different positions. Adjust as desired for 

the mounting location.

B )  Open the enclosure door. Pinch the top of the hinge rod using a nee-

dle-nosed pliers. Slide the door up and away to remove it. Set the door 

aside for later reattachment.

C ) Mount the box on a vertical surface, using supplied washers to protect 

the feet.

D )  Remove the clear plastic deadfront and keep the screws and washers 

in a safe place (for example, inside the removed enclosure door).

E )  Locate and remove the Spare Parts and XA-SLOT bags.

2

Foot mounting on 

back of unit

Mounting foot

Foot mounting screw

Foot mounted horizontally

Foot mounted at an angle

Foot mounted vertically

      

Remove an Unused Circuit Breaker (optional)

The combiner includes three 20 A, 2-pole circuit breakers for combining in-

puts and one single-pole 5A breaker for the 5A AC outlet. If required by local 

jurisdiction, you can remove unused 2-pole breaker(s) and install a blanking 

plate. Every AC Combiner comes with a blanking plate with screws. 
If you do not need to remove circuit break-

er(s), skip this step.

A )  Use a straight blade screwdriver to 

completely loosen the busbar side of 

the Line 1 and Line 2 terminal blocks 

(gray).

B )  Remove the load wire(s), if any, on the 

breaker you want to remove.

C )  Loosen the busbar lug(s) of only the 

breaker you want to remove.

D )  Release the DIN rail locking tabs of all 

breakers.

E )  Rock the breaker/busbar assembly to 

the left to release it from the DIN rail, 

and remove the breaker.

F )  Rock the breakers back to the right so 

they are seated back on the DIN Rail.

G )  Lock all of the breaker  DIN rail locking 

tabs.

H )  Tighten the busbar side of the  

Line 1 and Line 2 terminal blocks (gray) 

to 14 in-lbs (1.6 Nm).

I )  Verify that all busbar connections are 

tight.

J )  Position the blanking plate onto the dead front 

over the location of the removed breaker.

K )  Use a screwdriver and the two provided 

screws to secure the plate into place. 

3

Locking tabs

INSTALLATION — Part 1

You can complete Installation Part 1 before or after installing the PV 

system.

       Choose a location for the AC Combiner Box

A )  Install the AC Combiner Box in a readily accessible location. The best 

practice is to install at least four feet (1.2 meters) off the ground. 

However, never install below three feet (0.9 meters) off the ground. 

B )  Consider the dimensions of the combiner box, easy access, box 

height, and length of cable when selecting the location. Do not block 

the vents. The box is rainproof but not watertight.

NOTE

: You must mount the Combiner within 15 degrees of vertical.

1

Blanking 

plate

Warning! 

The AC Combiner has a pre-installed heat shield 

attached to the enclosure door. Do not remove the heat 

shield.

      

Drill Hole(s) to Accept Conduit

A )  A label on the outside of the combiner box indicates the best location to 

make a hole or holes to accept conduit fittings. Locate this label.

Best Practice:

 Use a stepped drill bit for making the conduit holes. Using 

a hole saw may crack the plastic housing. As an alternative, use a sharp 

chassis punch with caution. Drill only at the label location. Do not drill a 

hole in any other location on the box.

Note:

 The label template has three holes, but most applications 

require only two.

B )  Use the provided label as a template for typical conduit placement. The 

center of the holes on the label are marked with a “+” . 

C )  Use a snap punch or other type of center punch to prevent the drill from 

wandering. Drill a pilot hole with a smaller drill before using a step drill 

bit. 

D )  Remove the label after drilling.
E )  Use only UL-listed rain-tight or wet location hubs for wire entry into the 

enclosure.

4

Warning! 

Do not drill conduit holes on the top of the box 

or at any location that allows moisture ingress. This 

voids the warranty for the combiner box and the Envoy-S.

Note

If needed, you can request a cover for 

the 5A AC outlet from 

enphase.com/en-us/

support/contact

.

Loosen these 

screws

Summary of Contents for AC Combiner Box

Page 1: ...allation map for your records and to upload to Enlighten later G Note that installation of the Combiner has two parts To ensure successful device detection complete Part 2 after install ing any Enphase Microinverters and or Enphase AC Battery ies Note If needed you can find an installation map at the back of any Enphase Microinverter Quick Install Guide IMPORTANT This guide is for model XAM1 120 B...

Page 2: ...he dead front over the location of the removed breaker K Use a screwdriver and the two provided screws to secure the plate into place 3 Locking tabs INSTALLATION Part 1 You can complete Installation Part 1 before or after installing the PV system Choose a location for the AC Combiner Box A Install the AC Combiner Box in a readily accessible location The best practice is to install at least four fe...

Page 3: ...nto consideration the voltage drop rise and upstream breaker or fuse B The two DIN rail terminal blocks above the circuit breakers are the output connections Install the black wire into the lower terminal block and the red into the upper terminal block C Torque to 14 in lbs 1 6 Nm D Connect the neutral white to the neutral busbar E Connect the ground green or green yellow to the Ground busbar and ...

Page 4: ... do this you must create a protected route using conduit for the CT wires from the main load center to the Envoy S If you need to extend the wires refer to the Enphase Envoy S Installation and Operation Manual at enphase com support 7 Note Because of variance in load center design and main power feed there may not always be enough space to install consumption metering CTs DANGER Risk of electrocut...

Page 5: ... Device Communications LED flashes green while scanning solid green when all the devices you installed are communicating or solid amber if any devices are not communicating With both methods If the Device Communications LED remains solid amber see Troubleshooting b Verify System Configuration While still connected to the Envoy S with Installer Toolkit check the Over view screen for the following A...

Page 6: ...r network from the list of available networks If the wireless router does not support WPS you may be prompted to enter a password The Network Communica tions LED begins flashing green Within three minutes the Network Communications LED lights solid green indicating a successful connection to Enlighten If the Network Communications LED remains off or lights solid amber see Troubleshooting d Method ...

Page 7: ... steps Make sure that the broadband router is operational by checking that other devices at the site can access the network Be aware that metal enclosures or obstructions impede wireless communication If you cannot see your router or access point in the list on the Envoy or cannot maintain a connection it may be necessary to add a wireless repeater to extend the network range If you are using Wi F...

Page 8: ... Combiner Box read all instructions and cautionary markings in the technical description and on the equipment WARNING Use the circuit breakers in the Enphase AC Combiner Box only for serving Enphase equipment No other loads are allowed FCC Statement This equipment has been tested and found to comply with the limits for a Class B digital device pursuant to part 15 of the FCC Rules These limits are ...

Reviews: