background image

Commissioning Document

©2019 OutBack | an EnerSys company 

FA-KF-10/11/2019 

 Page 10 of 12 

Figure 11 – AC wiring of two SkyBoxes 

Summary of Contents for OutBack Power SkyBox SBX5048-120/240

Page 1: ...t power sold back to the grid In off grid operation the master unit controls only the AC output of the slave unit The slave unit maintains autonomy over its solar production and battery charging This...

Page 2: ...ave its own battery bank Units cannot share the same battery bank as each controls its own battery monitoring program Before mounting the Skyboxes ensure enough room exists around each unit to accommo...

Page 3: ...apid Shutdown Wiring Each SkyBox requires a connection between the rapid shutdown terminals for the inverter to operate Connect multiple units in series using the input and output terminals in each un...

Page 4: ...ry rating of 5 or higher CAT5 cable Each SkyBox is equipped with two Ethernet ports one labeled WALL and the other SKYBOX When stacking SkyBoxes the master SkyBox has a connection from its WALL port t...

Page 5: ...nit A Startup from battery will take approximately 45 60 seconds 2 Verify grid settings are the same between the units Network Settings SkyBox stacking requires static IP addressing in firmware versio...

Page 6: ...Only use if known otherwise leave blank Available Static IP Address 1 For master SkyBox Available Static IP Address 2 For slave SkyBox Subnet Mask 255 255 255 0 Use for both units Next on the master...

Page 7: ...Up To align the new settings between the SkyBoxes completely power down the system by opening all breakers Proceed through the following steps to re start the system If batteries are not present start...

Page 8: ...ter SkyBox only Optional External CT If using external current transducers CT connect them to the master unit Enable this function on the master SkyBox only Home screen SkyBox icon Configure Edit arro...

Page 9: ...unit requires a separate battery bank Q Version Match Verification Failure A This notification will appear when the firmware versions do not match between all units in the system This notification wil...

Page 10: ...Commissioning Document 2019 OutBack an EnerSys company FA KF 10 11 2019 Page 10 of 12 Figure 11 AC wiring of two SkyBoxes...

Page 11: ...OutBack Power Commissioning Document 2019 OutBack an EnerSys company FA KF 10 11 2019 Page 11 of 12 Figure 12 DC wiring of two SkyBoxes...

Page 12: ...17825 59th Avenue N E Suite B Arlington WA 98223 USA Email Support outbackpower com Website http www outbackpower com Other OutBack Power assumes no responsibility or liability for loss or damage whe...

Reviews: