OutBack Power
| Commissioning Document
©2019 OutBack | an EnerSys company
FA
-KF-10/
11
/2019
Page 5 of 12
Figure 5 – Ethernet connections
User Interface Setup
After making the physical connections and checking system voltages for the appropriate phase
relationship, apply power to the entire system using the startup procedure below.
Startup Process
If batteries are not present, start units from grid.
1. Shut battery breakers on each unit in the system, starting with the master unit.
A. Startup from battery will take approximately 45 – 60 seconds.
2. Verify grid settings are the same between the units.
Network Settings
SkyBox stacking requires static IP addressing in firmware version 1.3.27. In version 1.4 and greater,
static IP addressing is still preferred, but dynamic addressing is also acceptable.
Beginning with the master unit, log in as
Installer
. Under the
Network
tab edit menu, ensure the
Ethernet Connection
toggle is on
Wall
and set
DHCP enable
to
No
.
Repeat this step on the slave unit and change the
Ethernet Connection
to
SkyBox
.
(Home screen
Settings (gear)
Login
Network
Configure
Edit)
Figure 6 – Ethernet connection page, master and slave unit