background image

Commissioning Document

©2019 OutBack | an EnerSys company 

FA-KF-10/11/2019 

 Page 1 of 12 

Paralleling SkyBox 

This commissioning document covers the proper set-up of a system with two SkyBoxes connected in 

parallel and applies for firmware versions 1.3.27 and greater.  Parallel connection of multiple inverters 

is referred to as “stacking”; the combined system is referred to as a “stack”.  Paralleling two SkyBoxes 

enables system capacities of up to 10kW of power output.  At this time stacks with more than two 

SkyBoxes are not supported.  For a system power requirement that exceeds 10kW, please contact 

OutBack Sales.  

Theory of Operation 

Table 1 – Connected and Separate Components for Stacked Systems 

System Component 

Independent and 

Separate for Each Unit 

Co-dependent and 

Connected for Each Unit 

PV 

 

Battery 

 

Grid 

 

Load 

 

A SkyBox stack operates differently when on-grid and off-grid.  On-grid operation is straightforward; 

each unit acts independently to perform its programmed function.  The master SkyBox maintains 

communication with the slave unit and propagates any grid setting changes.  The master does not 

direct the operation of the slave unit.  Each unit independently maintains its own battery bank and 

harvests power from its own PV array unless the stack is set up to limit power sold back to the grid. 
In off-grid operation, the master unit controls only the AC output of the slave unit.  The slave unit 

maintains autonomy over its solar production and battery charging.  

This is the reason separate 

battery banks and separate solar arrays are required for each SkyBox in the stack. 

During a grid outage, the stack will power the loads on the protected loads panel by drawing power 

from the batteries and inverting it to produce the needed 120V/240VAC power.  The master unit 

takes control of the output voltage and modifies the current it is sending to the loads to maintain a 

120V/240VAC output.  The master then communicates this value to the slave unit so it contributes to 

maintaining the 120V/240VAC power.  If either unit is not harvesting enough PV to cover the power 

demanded by the loads, it will begin to discharge its battery.  Once EITHER unit reaches the minimum 

state-of-charge (SOC) set point, the entire stack will stop providing power to the loads.  The smallest 

of the independent battery banks determines the backup capacity for the stack.    

NOTE

: The minimum state-of-charge set point must allow enough remaining battery power to 

maintain SkyBox tare loss until the next solar day or until the grid returns.  
Once the grid returns, the master unit will synchronize with the grid.  Once the grid timer has expired, 

the master will close its grid relay and command the slave unit to do the same.  This returns the system 

to on-grid operation. 

Summary of Contents for OutBack Power SkyBox SBX5048-120/240

Page 1: ...t power sold back to the grid In off grid operation the master unit controls only the AC output of the slave unit The slave unit maintains autonomy over its solar production and battery charging This...

Page 2: ...ave its own battery bank Units cannot share the same battery bank as each controls its own battery monitoring program Before mounting the Skyboxes ensure enough room exists around each unit to accommo...

Page 3: ...apid Shutdown Wiring Each SkyBox requires a connection between the rapid shutdown terminals for the inverter to operate Connect multiple units in series using the input and output terminals in each un...

Page 4: ...ry rating of 5 or higher CAT5 cable Each SkyBox is equipped with two Ethernet ports one labeled WALL and the other SKYBOX When stacking SkyBoxes the master SkyBox has a connection from its WALL port t...

Page 5: ...nit A Startup from battery will take approximately 45 60 seconds 2 Verify grid settings are the same between the units Network Settings SkyBox stacking requires static IP addressing in firmware versio...

Page 6: ...Only use if known otherwise leave blank Available Static IP Address 1 For master SkyBox Available Static IP Address 2 For slave SkyBox Subnet Mask 255 255 255 0 Use for both units Next on the master...

Page 7: ...Up To align the new settings between the SkyBoxes completely power down the system by opening all breakers Proceed through the following steps to re start the system If batteries are not present start...

Page 8: ...ter SkyBox only Optional External CT If using external current transducers CT connect them to the master unit Enable this function on the master SkyBox only Home screen SkyBox icon Configure Edit arro...

Page 9: ...unit requires a separate battery bank Q Version Match Verification Failure A This notification will appear when the firmware versions do not match between all units in the system This notification wil...

Page 10: ...Commissioning Document 2019 OutBack an EnerSys company FA KF 10 11 2019 Page 10 of 12 Figure 11 AC wiring of two SkyBoxes...

Page 11: ...OutBack Power Commissioning Document 2019 OutBack an EnerSys company FA KF 10 11 2019 Page 11 of 12 Figure 12 DC wiring of two SkyBoxes...

Page 12: ...17825 59th Avenue N E Suite B Arlington WA 98223 USA Email Support outbackpower com Website http www outbackpower com Other OutBack Power assumes no responsibility or liability for loss or damage whe...

Reviews: