Mechanical installation
CE 4
10
Hauser
3.2.4
Installation point/hose installation
Installation hint
Sampling point
•
Medium removal for the pump and the sampling system must be taken from
representative point in the channel, i.e. not on the edge of the channel and not in the
sump or floor of the channel. A point offering a homogeneous mixture should be
selected.
•
There should always be enough medium available at the sampling point so that the a
good head of water is always available.
•
Suction hose is immersed by using a weight (see "Accessories").
Sampling hose installation
The sampling hose must always be installed with a downward slope from the
measurement station to the sampling point. Depending on the application, some hoses
may require frost protection.
Fig. 6:
Sampling hose installation
3.3
Mechanical installation
3.3.1
Tooling
The following tools are required to install the measurement station:
•
Electric drill with 12 mm concrete bit
•
M8 (4x) V2A rawl bolts
•
M8 (4x) V2A nuts and U washers
•
13 AF ring spanner
•
Screwdriver for power/signal terminals
•
Philips screwdriver