5.3
Installation for Ex version
1. Mounting of control system CPC 20 Z,
assembly and injector CYR 10 Z-E12.
2. Establish hose connections between assem-
bly and control cabinet.
3. Establish hose or pipe connections between
injector CYR 10 Z-E12 and cleaning port of
assembly.
4. Establish drive water connection to injector
CYR 10 Z-E12.
5. Connection of injector CYR 10 Z-E12 to
terminal strip in control cabinet:
−
Water valve to terminals 19 and 20
−
Cleaner valve to terminals 17 and 18.
6. Connection of measuring transmitter to
terminals 25/26 and 7-12.
7. Version Z-MID...
Connection of proximity switches to terminals
3+ and 4- and 5+ and 6-
8. Connection of compressed air to control ca-
binet and injector.
5.4
Start-up
Caution:
Check that all connections have
been properly made before power-
ing up the system!
Note:
Please familiarise yourself with the
operation of the Mycom CPM 152
before power-up.
1. Switch on the power supply.
2. Manual test of all functions.
3. Adjust cleaning times on built-in
program sequencer or measuring
transmitter CPM 152.
4. Test of automatic functions.
05PC20.CHP
autoclean CPC 20 / CPC 20 Z
5
Installation and start-up
Hauser
19