Wafer Sensors
Gaskets
The sensor requires a gasket at each of its connections to adjacent devices or piping. The gasket
material selected must be compatible with the process fluid and operating conditions. Metallic or
spiral-wound gaskets can damage the liner. Gaskets are required on each side of a
grounding ring. See Figure 9 below.
Alignment
1. On 1.5 - through 8-inch (40 through 200 mm) line sizes. Rosemount strongly
recommends installing the alignment spacers provided to insure proper centering of the
wafer sensor between the process flanges. The smaller line sizes, 0.5 and 1 in. (15 and
25 mm), do not require alignment spacers.
2. Insert studs for the bottom side of the sensor between the pipe flanges and center the
alignment spacer in the middle of the stud. See Figure 9 for the bolt hole locations
recommended for the spacers provided. Stud specifications are listed in Table 2.
3. Place the sensor between the flanges. Make sure that the alignment spacers are
properly centered on the studs. For vertical flow installations slide the oring over the stud
to keep the spacer in place. See Figure 9. To ensure the spacers match the flange size
and class rating for the process flanges see Table 3.
4. Insert the remaining studs, washers, and nuts.
5. Tighten to the torque specifications shown in Table 4 on page 13. Do not overtighten the
bolts or the liner may be damaged.
NOTE
Using carbon steel bolts on smaller line sizes, 0.5 and 1 in. (15 and 25 mm), rather than the
required stainless steel bolts, will degrade performance.
Figure 9. Wafer gasket placement
Table 2. Stud Specifications
Nominal Sensor Size
Stud Specifications
0.5 – 1 inch (15 – 25 mm)
316 SST ASTM A193, Grade B8M Class 1 threaded mounted studs
1.5 – 8 inch (40 – 200 mm)
CS, ASTM A193, Grade B7, threaded mounting studs
Spacer Installation
Horizontal meters Vertical meters