background image

Elterm M.M.Kaszuba Sp.J., ul. Przemyslowa 5, 86-200 Chelmno 

 

 

Terminal A – use to connect voltage free room temperature 
controller 

Terminal B – use to connect temperature sensor 1 to boiler’s 
body – central heating function (CH) 

Terminal  C  -  use  to  connect  temperature  sensor  2  to  hot 
water tank equipped with coil – hot utility water (HUW) 

LED display, signaling system and control 

 

 

 

 

 

 

 

Boiler 

 power 

Manual power 

distribution (%) 

Power 

modulation 

Power supply 

230/400V 

Safety  

fuses (A) 

Power cord 

(mm²) 

Heated area A 

(m²)* 

Heated area B 

(m²)** 

4 kW 

100 – 67 – 33 

by 1/3 

1 phase 

1 x 20 

3 x 2,5 

~ 50 

~ 70 

4 kW 

100 – 67 – 33 

by 1/3 

3 phases 

3 x 6 

5 x 1,5 

~ 50 

~ 70 

6 kW 

100 – 67 – 33 

by 1/3 

1 phase 

1 x 32 

3 x 4,0 

~ 70 

~ 100 

6 kW 

100 – 67 – 33 

by 1/3 

3 phases 

3 x 10 

5 x 2,5 

~ 70 

~ 100 

9 kW 

100 – 67 – 33 

by 1/3 

1 phase 

1 x 40 

3 x 10,0 

~ 110 

~ 150 

9 kW 

100 – 67 – 33 

by 1/3 

3 phases 

3 x 16 

5 x 2,5 

~ 110 

~ 150 

12 kW 

100 – 67 – 33 

by 1/3 

1 phase 

1 x 63 

3 x 10,0 

~ 150 

~ 210 

12 kW 

100 – 67 – 33 

by 1/3 

3 phases 

3 x 20 

5 x 4,0 

~ 150 

~ 210 

15 kW 

100 – 67 – 33 

by 1/6 

1 phase 

1 x 80 

3 x 10,0 

~ 180 

~ 250 

15 kW 

100 – 67 – 33 

by 1/6

 

3 phases 

3 x 25 

5 x 4,0 

~ 180 

~ 250 

18 kW 

100 – 67 – 33 

by 1/6

 

3 phases 

3 x 32 

5 x 6,0 

~ 220 

~ 310 

21 kW 

100 – 67 – 33 

by 1/6

 

3 phases 

3 x 40 

5 x 6,0 

~ 260 

~ 360 

24 kW 

100 – 67 – 33 

by 1/6

 

3 phases 

3 x 40 

5 x 10,0 

~ 300 

~ 400 

27 kW 

100 – 67 – 33 

by 1/6 

3 phases 

3 x 50 

5 x 16,0 

~ 220 - 380 

 

30 kW 

100 – 67 – 33 

by 1/6 

3 phases 

3 x 50 

5 x 16,0 

~ 240 - 400 

 

33 kW 

100 – 67 – 33 

by 1/6 

3 phases 

3 x 50 

5 x 16,0 

~ 260 - 450 

 

36 kW 

100 – 67 – 33 

by 1/6 

3 phases 

3 x 63 

5 x 16,0 

~ 280 - 480 

 

39 kW 

100 – 67 – 33 

by 1/6

 

3 phases 

3 x 80 

5 x 25,0 

~ 290 - 500 

 

42 kW 

100 – 67 – 33 

by 1/6

 

3 phases 

3 x 80 

5 x 25,0 

~ 300 - 520 

 

45 kW 

100 – 67 – 33 

by 1/6

 

3 phases 

3 x 80 

5 x 25,0 

~ 320 - 570 

 

48 kW 

100 – 67 – 33 

by 1/6

 

3 phases 

3 x 80 

5 x 25,0 

~ 340 - 600 

 

* Heated area A – boiler as main source of heat       ** Heated area B – boiler as alternative source of heat 

 

Exact cable cross section must be matched by qualified electrician based on local conditions analysis. 

1. LED display 
2. CH operation diode (AsD) 
3. HUW operation diode (AsD) 
4. OK/ON/OFF button 
5. LEFT – change button 
6. DOWN – decrease value 
8. Diode – °C 
9. Diode – power distribution 
10. Diode – operating time 
11. UP – increase value 
12. ON green diode 
13. RIGHT – change button 
14. OFF red diode 
 

Summary of Contents for redline asbill

Page 1: ...ntral heating systems Electric heating boiler SilverLine series RedLine series AsP Wachmistrz Venus Venere AsBN Rotmistrz Earth Terra AsZN Major Mars Marte AsD Brygadier Jupiter Giove AsBI Działon Saturn Saturno AsMB Mobilny Mobile Mobil AsHZ Husarz Comet Cometa AsBIII Batalion Star Stella Please see video prior installation ...

Page 2: ... BOILERS for more detailed pictures please see www elterm pl Dimensions and components of AsBN boiler Dimensions and components of AsP boiler Dimensions and components of AsD boiler Dimensions and components of AsZN boiler Dimensions and components of AsBI boiler Dimensions and components of AsMB boiler ...

Page 3: ...g systems safety unit expansion vessel and circulation pump is included AsD boiler in closed central heating system this model is designed for autonomous operation in both open and closed central heating systems safety unit expansion vessel and circulation pumps are included Additional water tank with coil at least 12kW is needed for proper boiler operation 1 External metal cast 2 Mounting plate 3...

Page 4: ...ase power supply 400V 3N 50Hz Models with 4 6 9 12 and 15kW powers are also available without any processing in 1 phase version 230V 1N 50Hz greater powers can also be prepared in 1 phase version upon request Boiler s power supply is connected to terminal strip labeled as L1L2L3N PE wire needs to be connected to screw on mounting plate Technical data table below provides information on the cross s...

Page 5: ...e 1 x 80 3 x 10 0 180 250 15 kW 100 67 33 by 1 6 3 phases 3 x 25 5 x 4 0 180 250 18 kW 100 67 33 by 1 6 3 phases 3 x 32 5 x 6 0 220 310 21 kW 100 67 33 by 1 6 3 phases 3 x 40 5 x 6 0 260 360 24 kW 100 67 33 by 1 6 3 phases 3 x 40 5 x 10 0 300 400 27 kW 100 67 33 by 1 6 3 phases 3 x 50 5 x 16 0 220 380 30 kW 100 67 33 by 1 6 3 phases 3 x 50 5 x 16 0 240 400 33 kW 100 67 33 by 1 6 3 phases 3 x 50 5 ...

Page 6: ...llation if it isn t please turn the boiler off and on again to repeat activity 4 For AsD model only LED display shows number 50 it represents current HUW temperature set on boiler bottom line visible on display Increase required temperature decrease required temperature confirm required temperature go to CH temperature setting 5 LED display shows number 20 it represents current CH temperature set ...

Page 7: ...y decrease temperature confirm setting 70 is recommended go to P05 function P05 Maximum boiler operating temperature HUW AsD model only Shows set operating temperature increase temperature up to 65 C decrease temperature down to 5 C confirm setting 50 is recommended go to P06 function P06 Boiler operation hysteresis Shows current hysteresis setting increase value 2 6 C decrease value 5 1 C confirm...

Page 8: ... lower line blinking Do not remove boiler external metal casing once device remains turned on In case boiler is activated by mistake with no water inside wait until heaters cool down fill device with water and switch it on again Under no circumstances fill device with cold water when heaters are still hot Once water in central heating system is heated system should be bled once again special atten...

Page 9: ...ween boiler and room thermostat Room temperature reached already idle time Wait for room temperature drop verification 5 LED display shows one of the below message E01 sensor error short circuit insufficient resistance e g sensor wire damaged E02 sensor error excessive resistance sensor not connected wire broken terminals not tightened properly on terminal strip Temperature not measured damaged se...

Page 10: ...requirements concerning Ecodesign for energy related products Attachment 13 EU Commission regulation nr 622 2012 With regard to Ecodesign requirements for glandless standalone circulators and glandless circulators integrated in products and that the standards hereinafter referred to have been duly applied and observed The harmonized standards applicable to the product to which this declaration of ...

Page 11: ...e or assembly that is not in compliance with the user manual etc or in the event the guarantee is invalid the costs of repair and travelling are borne by the claimant 6 Failure on the part of the user to follow the serviceperson s recommendations provided in the guarantee repair protocol results in the guarantee being suspended until such recommendations are implemented Do not call servicemen with...

Page 12: ...12 Elterm M M Kaszuba Sp J ul Przemyslowa 5 86 200 Chelmno Our other products For more information please visit www elterm pl ...

Reviews: