Commissioning and decommissioning
6.1.1 Checking the rotation direction
The intended direction of rotation of the drive
shaft is shown by the rotary direction arrow
(Fig. 2/O) on the motor fl ange.
a) Start the motor briefl y (max. two seconds) to
check the direction of rotation. When looking at
the motor fan, it must rotate anti-clockwise.
NOTICE
Incorrect direction of rotation
Running in reverse for a long time may damage the
machine.
Use a phase sequence indicator to check the direc-
tion of rotation (
clockwise rotating fi eld
).
6.2 Decommissioning/
storing
Stop the machine
a) Switch the machine off.
b) If available close the cut off device in the
suction and pressure pipe.
c) Disconnect the machine from the electricity
source.
d) Depressurise the machine: Open the pipes
slowly.
The pressure reduces slowly.
e) Remove the pipes and hoses.
f) Seal the connections for suction and pressure
nozzles using adhesive foil.
g) Insert the desiccant bag into the fi lter housing.
see also Section 3.2.1, Page 11
6.3 Re-commissioning
a) Check the condition of the machine (cleanliness,
cabling etc.).
b) Remove the desiccant bag from the fi lter hous-
ing.
For installation see Section 5 Page 14
For commissioning see Section 6.1 Page 17