64
Boiler Manual
PART 11: START-UP PROCEDURES FOR THE INSTALLER
(CONTINUED)
or the system sensor is defective. The cascade
system will still function in this situation and will
function with reduced efficiency. All boilers will
run simultaneously rather than in a staged fash-
ion. The second line indicates the status of the
system pump output of the cascade system. This
screen will alternate with the default screen every
5 seconds or, it can be accessed by pressing the
key from the default screen.
CASCADE TT 0123 567
SYS PUMP ON 12:47P
Description: This screen shows information about
the cascade status. The TT in the center of the top
line shows that the cascade demand is coming
from the TT contact being closed. You may also
see DHW if the demand is from a DHW sensor or
0-10 if the demand is from a 0-10 volt input. The
following numbers show which boiler addresses
are currently communicating to the master. If a
boiler address is not used or not communicating,
the number will not show on the display. In the
example above, boiler address #4 is not commu-
nicating. When a boiler in the system is firing, its
address number will alternate with a ‘.’ to signify it
is firing. The bottom line shows the status of the
system pump output contacts.
Press the
key,
CASCADE PWR
100%
PRESENT 01234567
Description : This screen shows the overall cas-
cade power output. The range of this value is
the number of boilers communicating with the
master x 100 so in the previous screen, the max-
imum cascade power is 800%. The second line
shows which boiler addresses are communicat-
ing with the master boiler.
Press the
key,
CASCADE SYST
118°F
CASCADE SET
190°F
Description: This screen shows the current sys-
tem temperature sensor reading on the top line
and the cascade system temperature setting on
the bottom line.
Press the
key,
BOILER 0
100 %
BOILER 1
56 %
Description: This screen shows the current cas-
cade power output on a per connected boiler
basis for boilers addressed as 0 and 1. In the
above screen, boiler 0 is at 100% firing rate and
boiler 1 is at 56% firing rate. If this were a 2 boil-
er system, the ‘CASCADE PWR’ screen above
would now be at 156%
Press the
key,
BOILER 2
0 %
BOILER 3
0 %
Description: This screen shows the current cas-
cade power output on a per connected boiler
basis. This screen is the same as the one above
except that it shows the power output of boilers
addressed as 2 and 3
Press the
key,
BOILER 4
0 %
BOILER 5
0 %
Description: This screen shows the current cas-
cade power output on a per connected boiler
basis. This screen is the same as the one above
except that it shows the power output of boilers
addressed as 4 and 5
Press the
key,
BOILER 6
0 %
BOILER 7
0 %
Description: This screen shows the current cas-
cade power output on a per connected boiler
basis. This screen is the same as the one above
except that it shows the power output of boilers
addressed as 6 and 7.
Summary of Contents for EL-110 LP
Page 48: ...47 Boiler Manual PART 8 FIELD WIRING CONTINUED Fig 8 5 LP 293 J Rev 10 1 09 ...
Page 49: ...48 Boiler Manual PART 8 FIELD WIRING CONTINUED Fig 8 5 LP 293 J Rev 1 14 10 ...
Page 83: ...82 LP 172 REV 2 16 06 ...
Page 84: ...83 LP 172 REV 2 16 06 ...
Page 85: ...84 MAINTENANCE NOTES ...
Page 86: ...85 MAINTENANCE NOTES ...
Page 87: ...86 MAINTENANCE NOTES ...
Page 88: ... 2003 2010 Heat Transfer Products Inc www HTproducts com LP 293 REV 01 06 10 ...