16 www.electrolux.com
the connecting pipe, drain pipe and
cables.
• To balance the ceiling and to avoid
vibration, please enforce the ceiling
when necessary.
2.
Please select the position of
installation hooks according to the
hook holes on the installation board.
• Drill four holes of
ø
12mm, 50~55mm
deep at the selected positions on the
ceiling. Then embed the expansible
hooks (ttings).
• Face the concave side of the installation
hooks toward the expansible hooks.
Determine the length of the installation
hooks from the height of ceiling, then
cut off the unnecessary part.
• If the ceiling is extremely high, please
determine the length of the installation
hook according to facts.
Product dimension
Fig.13
Fig.14
• Cut the installation hook open in the
New built houses and ceilings middle
position, then use apropriate length of
reinforcing rod (
ø
12) to weld together
The length could be calculated from
Fig.15: Length=210+L(in general, L is half
of the whole length of the installation hook)
Fig.15
3.
Please adjust the hexangular nuts on
the four installation hooks evenly, to
ensure the balance of the body.
• Use the lever indicator check the lever
from four sides of the main body. (Refer
to Fig.16)
Fig.16
• If the drainpipe is awry, leakage will
be caused by the malfunction of the
waterlevel switch.
• Adjust the position to ensure the gaps
between the body and the four sides of
ceiling are even.
• The body’s lower part should sink into
the ceiling for 10~12mm.
• Locate the air conditioner rmly by
wrenching the nuts after having
adjusted the body’s position well.
A
285
600
L
10-12
176
34
Drain side
(Unit: mm)
545 (Hook-location)
570 (Body)
647 (Panel)
523 (Hook-location)
570 (Body)
647 (Panel)
Body
Nut
Ceiling
Hook
Panel
Body
Ceiling
H (ceiling height)
Horizontal
indicator