Installation

Attention!

 Make sure that the short ends are staggered at least 200 mm (8”). 

Attention!

 When installing Long format floor boards, 

the short ends must be staggered by at least 500 mm.

 

ƒ

In the case of products supplied with a bevel and / or with a special pattern (e.g. tiles decor), ensure the offset is even according 
to the bevel and / or pattern.

 

ƒ

You install the first board of the third row by inserting the tongue on the long side into the groove on the long side of the second 
row diagonally from above. Then, lower the board until it is lying flat. To install the second board of the third row, once again tilt 
the long edge with the tongue down and slide it into the groove on the long side of the second row. With the board in this tilted 
position, now slide it towards the end of the first board in the third row until the frontal connection mechanisms are above each 
other so they fit perfectly. Once again, lock the long edge by lowering the board and the front by pushing until you can feel it lock.

 

ƒ

Install all remaining boards for the third row as described above, and cut the last board to fit.

 

ƒ

All the following rows can be started with the leftover piece of the previous row if this is at least 200 mm long or 500 mm for Long 
format floor boards.

 

ƒ

You can continue to install board after board now. 

In order to prepare the last row of boards for installation, take the board and place it exactly on top of the row before last. By means 
of a residual board (board width), it is possible to transfer the wall structures to the board within a pre-chosen distance.

Class 31, 32 and 33 Commercial Applications

2

2

3

3

GLUE

1

GLUE

1

Commercial areas are exposed to various levels of moisture and because of this, additional sealing with PVAC glue (D3), is 
mandatory in such applications. The sealing glue should be applied on the long and short side of the tongue of the board being 
installed so that it can leak out along the full length of the connection at the top when the boards are joined together. Make sure 
that there is no gap in the flooring joints under the glue which has oozed out. Excess sealing glue is easy to remove from the surface 
immediately or after a short drying period. 

(

Attention!

 Due to the profile geometry, a proportionate amount of glue is to be applied, particularly on the short side.)

Built-in kitchens / built-in cabinets

It is recommended to assemble built-in kitchens and cabinets before installation and to install the laminate or Comfort flooring to 
just behind the plinth panel.

Summary of Contents for UNIfit!

Page 1: ...Installation instructions for Egger Laminate and Comfort flooring with UNIfit installation system...

Page 2: ...M For calcium sulphate screeds calcium sulphate floating screeds 0 5CM heated screeds 0 3CM These values apply to screeds without additives With the use of additives and in case of fast setting screed...

Page 3: ...heating engineer installer floor covering manufacturer must work together in a coordinated manner All surface heated flooring requires appropriate planning and coordination of the heating system and s...

Page 4: ...nate flooring and Comfort flooring elements are installed at right angles to the floorboards Elastic flooring surfaces PVC linoleum vinyl The use of flexible floor coverings meets the damp proofing re...

Page 5: ...one at right angles to the boarding or the direction of the strip parquet wooden floor Planning the first row First the room must be measured to determine whether the width of the first row should be...

Page 6: ...sides of both elements push against each other and fits perfectly Once again lock the longitudinal connection by lowering and at the same time the frontal connection by pushing until you can feel the...

Page 7: ...leftover piece of the previous row if this is at least 200mm long or 500mm for Long format floor boards You can continue to install board after board now In order to prepare the last row of boards for...

Page 8: ...and tapping block Figure 1b 1c On door frames that cannot be shortened e g made of metal the fitted expansion joint must be sealed or covered with an elastic jointing material or suitable end profile...

Page 9: ...ort flooring immediately Steam cleaners should not be used the exception being on Aqua Laminate Flooring Only clean laminate and Comfort flooring with a damp cloth Never use scouring or abrasive mater...

Page 10: ...3841 301 20222 flooring egger com EGGER Drevprodukt Gagarin Ezhvinsky proezd 1 215010 Gagarin Oblast Smolensk Russia T 7 48135 79 300 F 7 48135 79 311 info ru egger com EN_EGGER_flo_installation_inst...

Reviews: