E F A P O W E R E V - H C - I N S T A L L A T I O N A N D U S E R M A N U A L
19 | 28
6
START-UP
6.1
VERIFICATION AND INSPECTION
Check
if
the
bolts
of the AC and
protective
ground
cables of the EFAPOWER EV-HC Station are correctly
tightened
Check
the
resistance
between
the EFAPOWER
EV-HC
protective
ground
and
the
low
voltage
switchboard
ground
connection; the
value
must be
according
to
local
codes
Before switching ON all circuit breakers,
check
the
supply
voltage
according to voltage required in the
characteristics label.
6.2
SWITCH ON
BEFORE ATTEMPTING TO INSTALL OR START UP THE EFAPOWER EV-HV STATION THE USER MUST ENSURE
THAT THE SAFETY INSTRUCTIONS IN THIS MANUAL ARE CAREFULLY READ AND OBSERVED BY TECHNICALLY
COMPETENT PERSONNEL.
KEEP THIS MANUAL WITH THE EFAPOWER EV-HC STATION FOR FUTURE REFERENCE.
THIS EFAPOWER EV-HC STATION MUST NOT BE STARTED OR PUT INTO USE WITHOUT HAVING BEEN
COMMISSIONED BY A FULLY TRAINED AND AUTHORIZED PERSON
ALL SERVICING MUST BE PERFORMED ONLY BY QUALIFIED PERSONNEL. DO NOT ATTEMPT TO SERVICE THE
EFAPOWER EV-HC STATION YOURSELF.
BY OPENING THE EV-HC
STATION’S
COVERS YOU RUN RISK OF EXPOSURE TO DANGEROUS VOLTAGES!
IN CASE OF ANY KIND OF DOUBT REGARDING THIS, PLEASE CONTACT:
EFACEC WILL ASSUME NEITHER RESPONSIBILITY NOR LIABILITY DUE TO INCORRECT OPERATION OR
MANIPULATION OF THE EFAPOWER EV-HV STATION.
EFACEC HAS TAKEN EVERY PRECAUTION TO PRODUCE AN ACCURATE, COMPLETE AND EASY TO UNDERSTAND
MANUAL AND WILL THEREFORE ASSUME NO RESPONSIBILITY NOR LIABILITY FOR DIRECT, INDIRECT OR
ACCIDENTAL PERSONAL OR MATERIAL DAMAGE DUE TO ANY MISINTERPRETATION OR UNDESIRED MISTAKES
IN THIS MANUAL.
THIS MANUAL MAY NOT BE COPIED NOR REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION OF EFACEC
Rua Eng. º Frederico Ulrich - Apartado 3078
4471-907 MOREIRA MAIA - PORTUGAL
Tel: (+351) 229403241 - Fax: (+351) 229403209
[email protected]
www.electricmobility.efacec.com