| Installing the Switch
Grounding the Chasis
– 37 –
This switch supports 1000BASE-LX5, 1000BASE-LX15, 1000BASE-LHX,
1000BASE-ZX, and 100BASE-FX SFP-compatible transceivers. To install an SFP
transceiver, do the following:
1.
Consider network and cabling requirements to select an appropriate SFP
transceiver type.
2.
Insert the transceiver with the optical connector facing outward and the slot
connector facing down. Note that SFP transceivers are keyed so they can
only be installed in one orientation.
3.
Slide the SFP transceiver into the slot until it clicks into place.
G
ROUNDING
THE
C
HASIS
Before powering on the switch, ground the switch to earth as described below:
1.
Ensure the rack on which the switch is to be mounted is properly grounded
and in compliance with ETSI ETS 300 253
2.
Ensure that there is a good electrical connection to the grounding point on
the rack (no paint or isolating surface treatment.)
3.
Disconnect all power cables to the switch.
4.
Then attach the grounding wire to the grounding point on the rack.
N
OTE
:
SFP transceivers are hot-swappable. The switch does not need to
be powered off before installing or removing a transceiver. However,
always first disconnect the network cable before removing a
transceiver.
N
OTE
:
SFP transceivers are not provided in the switch package.
C
AUTION
:
The earth connection must not be removed unless all supply
connections have been disconnected.
Summary of Contents for ECS4810-12M
Page 1: ...Installation Guide www edge core com 12 Port Gigabit Ethernet Switch ECS4810 12M ...
Page 2: ......
Page 4: ......
Page 14: ...COMPLIANCES AND SAFETY STATEMENTS 14 ...
Page 20: ...TABLES 20 ...
Page 22: ...FIGURES 22 ...
Page 44: ...CHAPTER 2 Installing the Switch Connecting to the Alarm Port 44 ...
Page 52: ...CHAPTER 3 Making Network Connections Cable Labeling and Connection Records 52 ...
Page 56: ...APPENDIX A Troubleshooting In Band Access 56 ...
Page 72: ...GLOSSARY 72 ...
Page 75: ......