Electronic control

Line current is sensed by internally mounted current 

sensing transformers. When current in excess of the 

minimum trip value is detected, the control initiates a signal 

which trips the faulted phase or phases, as applicable.
Refer to the applicable Installation and Operation manuals 

for control operation and setting procedures.
For Tri-Phase and TPG Controls:

 

MN285008EN: Tri-Phase, TPG and TPG with SCADA 

Electronic Control, Installation and Operation Instructions.

For Edison Idea Relays:

 

CA165005EN: iTAP-265 Dual Overcurrent Relay

 

Service Information S165-260-1, Use and Operations 

Manual for the iTAP-260 Underground Distribution VFI 

Switchgear Controller.

 

CA165002EN: iDP-210 Feeder Protection Relay

Loadbreak switch

In many configurations the Type RVAC switch is integrated 

within the VFI switchgear. Refer to the Operation section 

of 

MN285005EN Type RVAC Fluid-Insulated Vacuum 

Switchgear; Installation, Operation, and Maintenance 

Instructions

 for operation information for the RVAC switch. 

Vacuum fault interrupters

Load and fault interruption takes place within sealed vacuum 

interrupters (

Figure 1

). Vacuum interrupters provide fast, low 

energy arc interruption and produce no arcing by-products to 

contaminate the insulating fluid.

Figure 1 .  Vacuum fault interupter assembly

Bushings

600 A deadbreak aluminum type bushings, when furnished, 

conform to IEEE Std 386™-2006 standard. The standard 

200 A interface for 15 and 25 kV class underground 

distribution switchgear is an Eaton’s Cooper Power series 

200 A bushing well. For 35 kV class, the standard 200 A 

interface is an Eaton’s Cooper Power series 200 A one-piece 

loadbreak bushing. Both conform to IEEE Std 386™-2006 

standard.
Bushings are mounted in-line and are located a minimum of 

610 mm (24 inches) above the pad.

13

Figure 2 .  VFI switchgear components

Fluid Drain Plug and Sampler 

(not visible in view)

Grounding Lugs 

(not visible in view)

Bushings  

Wells

Tri-Phase  

Control

Recessed Lifting Provisions 

(not visible in view)

Interruptor Operating Handle

Fluid Level Sight Glass

Semaphores

Operation One-Line 

Diagram

Tri-Phase 

Control

Figure 1 . Vacuum fault interrupter assembly

Flux Shift 

Tripper

Vacuum Fault 

Interrupter

Summary of Contents for VFI

Page 1: ...Type VFI Fluid insulated Switchgear Installation Operation and Maintenance Instructions COOPER POWER SERIES Underground Distribution Switchgear MN285006EN Effective March 2018 Supersedes December 2015...

Page 2: ...PARTICULAR PURPOSE OR MERCHANTABILITY OTHER THAN THOSE SPECIFICALLY SET OUT IN ANY EXISTING CONTRACT BETWEEN THE PARTIES ANY SUCH CONTRACT STATES THE ENTIRE OBLIGATION OF EATON THE CONTENTS OF THIS D...

Page 3: ...binet construction 3 Standard features 3 Interrupter duty cycle 3 Switch test sequence 3 Finish 3 Nameplate 3 Operating handles 3 Weight 4 Special certifications 4 INSTALLATION PROCEDURE 4 OPERATION 5...

Page 4: ...hazardous situation which if not avoided will result in death or serious injury WARNING Indicates a potentially hazardous situation which if not avoided could result in death or serious injury CAUTION...

Page 5: ...e pallet Improper handling can cause damage to the switchgear If the switchgear is to be stored for any appreciable time before installation provide a clean dry storage area Be careful during handling...

Page 6: ...llation Operation and Maintenance Instructions for operation information for the RVAC switch Vacuum fault interrupters Load and fault interruption takes place within sealed vacuum interrupters Figure...

Page 7: ...37 74TM 2003 standard Padlocking provisions Provisions are included for padlocking the cabinet in order to prevent unauthorized door opening The cabinet must be locked at all times to prevent accident...

Page 8: ...tances where a UL listing is required Figure 3 VFI switchgear operating handle three phase ganged operation Figure 4 VFI switchgear operating handles single phase operation Installation procedure WARN...

Page 9: ...T223 2 5 Ground switchgear Switchgear must be adequately grounded Install a permanent low resistance ground connection to the switchgear tank Grounding provisions are provided near the bottom of the t...

Page 10: ...aintenance Instructions for operation information for the RVAC switch Loadbreak switch In most configurations a Type RVAC loadbreak switch is integrated within the VFI switchgear The switch s push to...

Page 11: ...ith sampler at the bottom of the tank If moisture is found in the tank refill with clean dry insulating fluid WARNING Hazardous voltage This equipment must be de energized and grounded prior to conduc...

Page 12: ...ry T239 2 Use the following fluid sampling guidelines to prevent contamination and to safely extract fluid samples 1 De energize and ground the switchgear prior to sampling fluid 2 Where local governi...

Page 13: ...from altering the moisture content of the sample Leave about one inch of air space in the container to account for thermal expansion 15 Retighten sampling valve to finger tight plus a 1 4 turn Reinsta...

Page 14: ...e if moisture levels are rising Refer to the Fluid sampling guidelines section in this manual If moisture levels increase determine leak point and repair Process or replace the fluid if water conent h...

Page 15: ...arts the switchgear and high voltage transformer must be placed in a suitable test cage and all proper grounding procedures must be observed With the vacuum interrupters open manual operating handle s...

Page 16: ...es Eaton com cooperpowerseries 2018 Eaton All Rights Reserved Printed in USA Publication No MN285006EN March 2018 KA20480375 Rev 09 Eaton is a registered trademark All trademarks are property of their...

Reviews: