57
5. Installation
5.7 Multiple Battery Pack Connections
CAUTION!
Ensure correct polarity of the battery string series connection. DO NOT mix old and new batteries,
different brands of batteries or batteries with different capacities.
WARNING!
Ensure correct polarity of battery string end connections to the battery circuit breaker, and from
the battery circuit breaker to the UPS terminals, i.e. (+) to (+), (-) to (-) and (N) to (N). Disconnect one
or more battery cell links in each tier. Do not reconnect these links and do not close the battery
circuit breaker unless all connections have been properly checked and approved.
5.7.1 Models BP240V09 / BP240V09K / BP240V09-NIB
Note:
The BP240V09 / BP240V09K / BP240V09-NIB battery cabinets are compatible only with 10kVA to 20 kVA UPS systems.
UPS
Battery cabinet 1 Battery cabinet 2
Figure 5-57: Multiple Battery Pack (80 x 9Ah)
Connections for BP240V09 / BP240V09K / BP240V09-NIB – 10 kVA, 15 kVA and 20kVA UPS
Summary of Contents for Smart Online S3M BP240V09
Page 38: ...38 5 Installation Figure 5 32 Wiring Diagram for Installation of 80 Batteries ...
Page 46: ...46 5 Installation Figure 5 41C Front Layer 3 Layer 2 Layer 1 Rear ...
Page 49: ...49 5 Installation Figure 5 44A 2 Remove top right side and left side plates Figure 5 44 ...
Page 54: ...54 5 Installation 14 Reinstall the covers and the screws Figure 5 53 Figure 5 53 ...
Page 113: ...113 5 Instalación Figura 5 32 Diagrama de Cableado para la Instalación de 80 Baterías ...
Page 121: ...121 5 Instalación Figura 5 41C Frente Capa 3 Capa 2 Capa 1 Atrás ...
Page 129: ...129 5 Instalación 14 Reinstale las cubiertas y los tornillos Figura 5 53 Figura 5 53 ...
Page 196: ...196 5 Installation Figure 5 41C Avant Couche 3 Couche 2 Couche 1 Arrière ...
Page 204: ...204 5 Installation 14 Réinstaller les couvercles et les vis Figure 5 53 Figure 5 53 ...