INSTALLATION
Eaton BladeUPS Bar Installation Guide
S
164201723 Rev 2
www.eaton.com/powerquality
17
BladeUPS Bar Installation (Top Entry Wireway)
To install the BladeUPS Bar in a top entry rack:
1.
Remove the access cover and terminal block housing from the
wireway housing (see Figure 12). Retain the wireway terminal block
housing, wireway access cover, bolts, and screws. Leave the two
side brackets installed on the wireway housing (see side bracket
locations in Figure 13).
2.
Verify that the side brackets are in the most closed position and
that the adjustment screws are tightened to prevent the side
brackets from moving.
C
A
U
T
I
O
N
If the side brackets are loose, they can move during wireway placement and cause injury.
Wireway Terminal
Block Housing
Wireway Access Cover
Wireway
Housing
M6
12 Hex Bolts
(2 places)
M4
8 Pan-Head Screws
(9 places)
Figure 12. Wireway Disassembly
3.
Place the wireway housing into the top of the rack so that the
adjustable side brackets are nearest the front of the rack
(see Figure 13).
4.
Install an M6 hex nut onto each of the three wireway studs to
secure the wireway to the rear of the rack. Install the first stud in
the third hole location from the top. Do not tighten the nuts.
Figure 14 shows the nuts installed.