48
4–20kVA Users Guide P-164000669 4–20kVA Users Guide P-164000669—Rev 10
2.
If you are rack-mounting the EBM cabinet, refer to the UPS rack-mount installation procedure (see
). If not, proceed to the next step.
3.
Install the anchor brackets to the floor if applicable (see
).
4.
Push in the EBM DC emergency disconnect switch on the rear EBM panel and turn the switch lockout key
(see ).
NOTE
The UPS and EBM AC/DC terminal covers are shipped in the UPS and EBM accessory
kit and do not come installed on the UPS or EBM chassis.
5.
Route the EBM DC input/output cables to the terminal blocks as shown in (
).
NOTE
Torque the screws holding all input and output power conductors to the values specified
in
.
6.
Connect the EBM DC Cables to the applicable terminals by removing and reinstalling the screws onto the
terminal blocks. See
Figure 41. Connected EBM (No AC Input Option)
From previous
EBM
(if installed)
CN3
CN4
CN4
EBM
UPS
DC+
DC-
DC+
DC-
L1
G
N
L2
Screws
Screws
Ground
Lug
Cover
DC+ DC- DC- DC+
G L1 N L2
To UPS
DC input cables from
upstream EBM
(if installed)
Terminal
Block
Terminal
Block
Summary of Contents for 9PXM8S4K
Page 1: ...p n P 164000669 Revision 10 Eaton 9PXM UPS 4 20kVA Users Guide Eaton 9PXM UPS...
Page 4: ......
Page 8: ...viii 4 20kVA Users Guide P 164000669 4 20kVA Users Guide P 164000669 Rev 10 Table of Contents...
Page 12: ...xii 4 20kVA Users Guide P 164000669 4 20kVA Users Guide P 164000669 Rev 10 List of Tables...
Page 20: ...8 4 20kVA Users Guide P 164000669 4 20kVA Users Guide P 164000669 Rev 10 Physical Features...
Page 98: ...86 4 20kVA Users Guide P 164000669 4 20kVA Users Guide P 164000669 Rev 10 Display Menu Screens...
Page 104: ...92 4 20kVA Users Guide P 164000669 4 20kVA Users Guide P 164000669 Rev 10 Communication Slots...
Page 120: ...P 16400066910 P 164000669 10...