UPS Operating Instructions
Eaton 9EHD UPS (80-200 kVA, 380/400/415V) Installation and Operation Manual
6-21
6.4.8 Charger Control
To turn an individual UPS battery charger on:
1. Select the CONTROLS symbol on the main menu bar on the UPS requiring the charger to be turned on. The
System Control screen is displayed.
2. Select Battery on the System Control screen
3. On the Battery System Control screen, select the RESTING CHARGING command, then press the
RETURN pushbutton.
To turn an individual UPS battery charger off:
1. Select the CONTROLS symbol on the main menu bar on the UPS requiring the charger to be turned off. The
System Control screen is displayed.
2. Select Battery on the System Control screen.
3. On the Battery System Control screen, select the CHARGING RESTING command, then press the
RETURN pushbutton.
This UPS has a user initiated battery test intended to determine if the batteries are
able to support the load.
The battery test is only able to be initiated when the battery is fully charged. This
normally occurs within 72 hours of the start of a charging cycle. The command will
not be shown if the test is not able to be run.
NOTE 1
NOTE 2
6.4.9 Battery Test
To start an individual UPS battery test:
1. Select the CONTROLS symbol on the main menu bar on the UPS to be tested. The System Control screen
is displayed.
2. Select Battery on the System Control screen.
3. On the Battery System Control screen, select the RESTING TESTING command, then press the
RETURN pushbutton.