UPS System Installation
4-4
Eaton 9EHD UPS (80-200 kVA, 380/400/415V) Installation and Operation Manual
Figure 4-4. Rolling the Cabinet Down the Ramp
UPS System Installation
Eaton 9E UPS (40–60 kVA, 208/220V) Installation and Operation Manual P-164000058—Rev 2
4-5
Figure 4-4. Rolling the Cabinet Down the Ramp
For
Internal
Use
Only
4.3
External Battery Cabinet Installation
WARNING
•
In the event of malfunction, the battery cabinet chassis or battery cabinet frames may
become live!.
•
Special care should be taken when working with the battery cabinet associated with the
equipment. Ensure the battery number is suited to the setting of the battery charging voltage
before installing the battery. When the battery cabinet is connected the overall voltage
exceeds nominal voltage. It is very important to ensure that the batteries are installed
separately, in a dedicated battery cabinet.
•
Battery back-up time do not exceed one hour, if the battery setting shall be exceeded one
hour, consult to the professional personnel.
Before connecting the external battery, please read the notice and warning label on the battery cabinet.