UPS System Installation
Eaton 9EHD UPS (80-200 kVA, 380/400/415V) Installation and Operation Manual
4-13
a. Remove the small parts from the knockout in the right side plate.
b. Route the wiring (see Figure 4-12) to the wiring access (see Figure 4-12). Secure the wiring to the four
mounting clips provided using Zip ties.
c. Reinstall the wires to cover using the retained hardware.
d. Install the power terminal cover up and down sides using the provided hardware.
5. Route and install RJ-45 Controller Area Network (CAN) cables between the UPS cabinets. See Figure 4-10
and Figure 4-14 for wiring information.
6. Route and install pull chain wiring (Twisted Wires 0.5-2.0 mm
2
) between the UPS cabinets and cabinet
MOBs. See Figure 4-10, Figure 4-13, and Figure 4-14 for wiring information.
7. Reinstall the interface terminal cover using the retained hardware.
8. If wiring Mini-Slot connections, proceed to paragraph 4.5.3;
9. Install the power terminal cover right and left sides using the provided hardware.
4.5.3 Installing Mini-Slot Interface Connections
For installation and setup of an Mini-Slot card, contact an Eaton service representative (see paragraph 1.8)
To install wiring:
1. If not already installed, install the LAN drop.
2. Route and install the LAN and other cables to the appropriate Mini-Slot cards. See Figure 4-9 and
Figure 4-10 for Mini-Slot communication bay locations.
3. Refer to the manual supplied with the Mini-Slot card for operator instructions.
4. Install the power terminal cover using the provided hardware.
LAN drop for connection to UPS communications card is to be supplied by customer.