background image

Vantage 4000 

 
Materials Required

 

* 4 pigtail cap crimps (wire size 18-12) 
* 2 center conductor cap crimps (wire size 22-14) 
* Strips of splice wrap 
Crimp tool (customer supplied) 
Knife (customer supplied) 
Pointed tool (customer supplied) 
Junction box (customer supplied) 
  A cable connection kit may be purchased through Eastech Badger that will include the * items above 
(Part # 541874). 
  Trim each of the four cables at the junction box to 9 inches in length. Each of the four cables can now be 
prepared as described in the sequence following: 
 
  Using a knife, trim two inches of the outer jacket from each cable. The wire braid beneath the outer 
jacket must not be cut. 

See "A".

 

  Using a pointed tool, carefully comb out the outer braid of each cable as shown in "B". Form the combed 

braid into a pigtail dressed to the side of the cable as 
shown in "C". 
  Trim 1 inch of the inner jacket from each of the cables 
as shown in "D".  Again, use care not to cut the inner 
braid beneath the inner jacket. 
  Using a pointed tool, carefully comb out the inner 
braid "E" and form into a pigtail dressed to the same side 
of the cable as outer pigtail in "F". 

  Remove 1/2 inch of insulation from the inner conductor of each cable. Cut the outer pigtail to the same 
length as the inner pigtail on each cable. "G" depicts the completed preparation. 
 

Cable Termination

 

  Pull cables approximately 18 inches outside of junction box. Select one sensor cable and one cable from 
the electronic enclosure and place them side by side as shown in Fig. 1. Twist each cable's outer pigtails 

together, then the inner pigtails together and finally the center 
conductors together to form the cable splice. In similar fashion, 
connect the remaining sensor cable and the cable from the 
electronic enclosure. 
  Identification of upstream and downstream sensor cables must 
now be made. Connect a short wire from the center conductor 

splice to the inner shield pigtail splice on the upstream sensor 
cable. Using a multimeter determine the upstream sensor cable at 

the electronic enclosure end by continuity measurement. Identify the upstream cable for later termination. 
  Remove the shorting wire and using the cap crimps supplied, crimp the larger caps on each spliced 
pigtail and the small cap on the center conductor splice as shown in Fig. 2. Repeat this procedure for the 
second cable. 
  At this point turn power on at the electronics and verify that an OK signal condition appears  on the 
display. 
 
 

Turn power "OFF".

 

 

Using Splice Strips

 

1.  Remove cover off of strips 
2.  Totally wrap strips tightly around all of the splice connections. 
 
  The finished splices should be coiled inside the junction box. When properly placed, the splices should 
be clear of the junction box cover area. Proper sealing of the junction box is necessary for watertight 
integrity. 
 
  This completes the triax cable splice connection. 

 

Triax Cable Splice Procedure 

A       B        C      D        E         F          G

 

FIG 1 

FIG 2 

 

2-5 

Summary of Contents for Vantage 4000

Page 1: ...h the manual The change notice will identify the sections in this manual where the changes have occurred Vantage 4000 Table of Contents Scope 1 1 General Specifications 1 2 Installation Procedure 2 1...

Page 2: ...ata Logger Software CD Display Backlit LCD 128x64 Graphic Module Programming Front panel mounted 16 button keypad Computer or Palm Pilot Power 80 240 VAC 50 60 Hz or 12 28 VDC 350 mA continuous Accura...

Page 3: ...hinged door clasps on the front cover of the enclosure To open put thumb on one of the hinges pull toward the outside of the enclosure Once the hinge pops to the outside it will lower allowing the cl...

Page 4: ...Pull Box by others Flex Conduit by others Sensor Cable 1000ft max NEMA 4X IP66 Enclosure Sensor connections 1 2 14 NPT 7 8 entrance holes 3 places 2 2 Note The key will have to be left in the hinge ha...

Page 5: ...C power terminal is separate from the other two terminal strips The power terminal strip has three connections for High Low and Ground for AC voltage only Refer to the wiring diagram below for all int...

Page 6: ...cable and remove the middle cover 4 Remove middle shield Measure 5 8 from the end of the cable With a pair of small cutters cut the shield around the cable at the measured point and remove the cut of...

Page 7: ...inches outside of junction box Select one sensor cable and one cable from the electronic enclosure and place them side by side as shown in Fig 1 Twist each cable s outer pigtails together then the inn...

Page 8: ...g To adjust damping time 06 Lost Signal To adjust Lost signal time and Fail to zero or span 07 Flow Sim Flow simulation 08 Integrator To assign closure for contact integrator 09 Setpoints To assign se...

Page 9: ...s ENTER key and number 01 Flow Units Select the flow engineering unit desired by pressing the number in front of the selection Units available are 01 GPM gallons minute 09 LPD liters day 02 GPD gallon...

Page 10: ...sensor and is 640KHZ operating frequency 06 V30ST 640 is the small new style strap on sensor for high temperature applications and is 640KHZ operating frequency 07 V30L 640 is the large new style stra...

Page 11: ...pe Material screen Pipe Material The pipe material screen will allow you to select the pipe material for the unit Selections are Carbon Steel Stainless Steel PVC Cast Iron Ductile Iron Asbestos Cement...

Page 12: ...sensor placement on the pipe Selections are 01 Z Shot sensors are mounted on opposite sides of pipe 02 V Shot sensors are mounted on the same side of pipe 03 W Shot sensors are mounted on the same sid...

Page 13: ...ards To adjust Span Press the 6 key the cursor arrow will appear before the 6 20 mA line Press the 3 key for coarse adjustment or the 4 key for fine adjustment Now press the 1 key to adjust the mA upw...

Page 14: ...key the next screen to appear is the Lost Signal Action assignment In this screen the user will select the default for the 4 20mADC output during a lost signal condition The selections are 01 Fail to...

Page 15: ...t after the selection is entered Press the ENTER key The Setpoints must be assigned to a Relay 10 Relays Relay Assignment The next option in the program menu is the Relays screen To select this press...

Page 16: ...1 Not active 02 Setpoint 1 03 Setpoint 2 04 Setpoint 3 If set points are selected then the next screen will be storage rate times available 04 Log Channels There are up to 8 channels available for log...

Page 17: ...Display Mode 4 N A Model 4400 01 Display Mode 1 Flow Velocity Totalizer and Status 02 Display Mode 2 N A 03 Display Mode 3 N A 04 Display Mode 4 N A 05 Options N A 06 Totals Reset This option will re...

Page 18: ...s or omissions of others after shipment nor any consequential incidental or contingent damage whatsoever A claim for equipment damaged in transit is the sole responsibility of the customer NUCLEAR DIS...

Reviews: