Check Anode Rod(s) – After First Year
•
Repeat the inspection and maintenance as required on a once-a-year basis after the
first year, unless necessary to inspect more often.
Flush Tank
•
Turn OFF electric power.
•
Close the isolation valves between the GSTE storage water heater and other
EarthLinked
®
system components.
•
Close the main cold water supply isolation valve to the storage water tank/heater.
•
Open a faucet downstream of the hot water outlet on the storage water heater.
•
After connecting the storage water heater drain valve to a drain hose, open the drain
valve and drain the entire tank of water to an open drain.
•
Close tank drain valve.
•
Open the main cold water inlet valve and fill the storage water heater with clean water
until it is approximately 25% full.
•
Turn off the main cold water supply isolation valve, open storage water heater drain
valve, and observe the water coming out the drain valve going into the drain.
•
Continue to flush the tank as noted above until the water coming out the drain valve is
clear and free of sediment.
•
Close the drain valve and the faucet.
•
Open the main cold water supply valve and fill the storage water heater and piping
system with water.
•
Open the isolation valves between EarthLinked
®
system components and the storage
water heater and purge air from system.
•
Turn ON electric power and initiate normal system operation.
T&P Valve
Check the GSTE T&P Valve for proper operation by doing the following:
•
Turn OFF electric power.
•
Attach a drain hose to the valve, with water discharge directed to an open drain.
•
Lift the lever at the end of the valve several times.
•
The valve should operate freely and return to its original position properly.
•
If water does not flow out of valve, close main cold water supply isolation valve to the
system, and close isolation valves between EarthLinked
®
system components and the
storage water heater, and lower the water level to below the T&P valve.
•
Remove valve and inspect for corrosion or obstructions.
•
Replace with new valve if necessary. DO NOT REPAIR AND INSTALL THE FAULTY
VALVE.
•
Open the isolation valves between the EarthLinked
®
system components and the
storage water heater. Open the main cold water supply to fill the system. Purge air from
system.
•
Turn ON electric power and initiate normal system operation.
Summary of Contents for GSTE-119
Page 5: ...SWH IOM 08 10 Page 5 Figure 1 GSTE Storage Water Heater Description...
Page 7: ...SWH IOM 08 10 Page 7 Figure 2b Top of Tank Connections CWH...
Page 8: ...SWH IOM 08 10 Page 8 Figure 2c Electrical Field Wiring CWH...
Page 10: ...SWH IOM 08 10 Page 10 Figure 3b Top of Tank Connections DWM...
Page 11: ...SWH IOM 08 10 Page 11 Figure 3c Electrical Field Wiring DWM...
Page 13: ...SWH IOM 08 10 Page 13 Figure 4b Top of Tank Connections Desuperheater...
Page 14: ...SWH IOM 08 10 Page 14 Figure 4c Electrical Field Wiring Desuperheater...
Page 16: ...SWH IOM 08 10 Page 16 Figure 5b Top of Tank Hydronic Heating HWM...
Page 25: ...SWH IOM 08 10 Page 25...