![background image](http://html.mh-extra.com/html/duro-maxx/dm4p10k/dm4p10k_installation-and-owners-manual_2542529013.webp)
13
DM4P10K
July 2018
20. Have a certified electrician make the electrical connection
from power supply to the power unit.
Use separate circuit for power unit. Electrical Wiring must comply with local code. Protect each
circuit with time delay fuse or circuit breaker. For 208V-230V single phase, use 20 amp fuse.
21. Install the
“wire braded” Hydraulic Hose (#43) to the Fitting on the side of the Main side
Runway and attach the other end to the 90 degree Fitting on the Power Unit as shown in Fig.2.
22. Now raise the complete unit (Lift) and set at one of the bottom lock positions. Place level on
crossbeam.
23. Tighten Lock Ladder Rod Nut (#14) located on the top of each Column. This will raise the
corner of the lift to adjust for leveling. Each Column has this adjustment. Adjust the proper
columns to level the lift. Place a level on each runway and crossbeam and check for proper
levelness.
Note: You may have to loosen the Jam Nut under the Top Cap to make adjustments.
24. After leveling is complete, tighten the Jam Nut on the Lock Ladder underneath the Top Cap on
each post. This will secure the Lock Ladder in position.
25. Raise lift off all locks until cables are supporting the lift. Adjust the Cable
’s Nylon Lock Nut as
shown in Fig 7, located on the top of each post until lift is level on crossbeams and runways.
This will ensure the lift travels up and down level.
Note: You may need to use locking pliers to hold the Cable from turning when adjusting
the Nylon Nut. Make sure that threads engage through the nylon on each Nylon Nut.
26. Install Crossbeam Cover panels (#68, #69, #70 & #71) on both sides of Crossbeam. Also
install the Plastic
‘drip’ Board (#20 & #21) into the bracket slots on the underside of the
Mainside Runway.
27. Install Cover Plates (#55) to each end of Runways. Also insert Wheel Stops (#54) at front of
Lift, as shown below in Fig.10.
Fig. 10
28. Install
‘drive-on’ Ramps (#7) at rear of Lift. Also install and Foot Plate (#19) on the bottom of
Power Unit Column.
29. (Optional) Install the Jack / Tool Tray & Drip Trays between the Runways, if purchased.
NOTE: Ensure to lubricate ALL Cable Sheaves, Bearings and Shafts with grease prior to
operating Lift.
The Lift installation is now complete.