background image

TUF 100 ROOF 

fig. 1 

Step 1: Note: 

Condensation  can  form  on  the  under  side  of  shed  roof.  If  building  paper  is  required,  fit  now. 

Building paper will need to be supported by netting or roofing twine. 

 

 

 

Roof:

 Position Roof Sheets as shown in 

fig 1

. Make sure sheet joins at the back of the roof are flush. 

Rivet sheet joins, one rivet 200mm back from edge front and back. Fit two more rivets evenly spaced in cen-

tre of each join. 

Step 3:

 Line  up  ribs  on  the  roof  with  ribs  on  the 

walls. While someone holds the Front Plate 
straight,  nail  the  roof  to  Top  Plate  using 
one  40mm  Weatherseal  nail  beside  each 
rib. Repeat at the back. 

Step 4:

 Fit  Roof  Flashing  as  shown.  When  posi-

tioned correctly rivet through Roof Flashing 
into Roof Sheet joins. 

Step 2:

 Position  Roof  so  that  the  front 

overhang  measures  140mm. 
Rivet  roof  to  wall  sheets  using 
one  rivet  every  second  Rib.  Re-
peat  at  the  other  end  ensuring 
overhang measures 140mm. 

Summary of Contents for TUF 100

Page 1: ...Quality Made Affordable ASSEMBLY INSTRUCTIONS TUF 100 BASE SIZE 1140mm x 1690mm...

Page 2: ...checklist If you are making your own floor refer to Raised Base Plate section now Do not attempt to build your shed in high winds Beware of sharp edges Protect your eyes and ears Use electric tools w...

Page 3: ...00 PARTS LIST Assembly Instructions Roof Flashing End Wall Nogs Front Wall Nog Back Wall Nog 2 1 1 890 1 160 1 1 175 Red 45 x 45 H1 Red 70 x 45 H1 Red 45 x 45 H1 Yellow 45 x 45 H1 FLASHINGS Door Jambs...

Page 4: ...Ensure Green joins to Green and Red joins to Red See fig 2 for nailing detail on Top Front Plate 70x45mm Step 3 Position remaining End Frame on top of plates While someone sup ports frame nail in plac...

Page 5: ...Use ink to mark steel Step 1 Door Jambs Position left hand Door Jamb Flashing at correct measurement from left cladding detail and nail to Top Plate using a 30mm clout Do not fit 50mm nails at this s...

Page 6: ...m clout top and bottom Step 5 Drill a hole through Door Jamb Flashings and Wall Sheets top and bottom Nail with 50mm nails fig 1 Nail left hand Door Jamb Flashing to Stud using three 30mm Clouts at eq...

Page 7: ...d back Fit two more rivets evenly spaced in cen tre of each join Step 3 Line up ribs on the roof with ribs on the walls While someone holds the Front Plate straight nail the roof to Top Plate using on...

Page 8: ...ate Flashing and fit one rivet to top hinge While still hold ing in position fit one rivet to bottom hinge Step 3 Close door and check it fits correctly If not drill out rivets and make necessary adju...

Page 9: ...RITY DOOR Optional Step 1 Place shed in final position Check diagonal meas urements are equal and shed is level before fitting door Step 2 Hold Door in position approximately 5mm down from Top Plate F...

Page 10: ...l Sheets will then protrude 20mm below the Base Plate This will stop water flowing in between the Base Plate and Floor If you choose this option the Floor should be made 15mm smaller than Base Size No...

Page 11: ...in most environments The surface must be dry and free of dirt oil grease and other contaminants prior to painting but no weathering of the surface is required Zinc rich primers are recommended for us...

Page 12: ...nd very severe environmental situations or in any area where the mild steel corrosion rate as published by BRANZ exceeds 200g m2 3 Minimum maintenance must be carried out in accordance with instructio...

Reviews: