FRONT VIEW
DOOR JAMB
FLASHING
5
TUF 100 WALL CLADDING
fig. 1
fig. 2
To Avoid Corrosion:
Where at all possible try not to trap metal filings between two sheets. Remove all metal filings before riveting.
Carbon in pencils reacts with the Zinc/Aluminium coating on steel. Use ink to mark steel.
Step 1:
Door Jambs: Position left hand Door Jamb Flashing at
correct measurement from left
(cladding detail)
and nail
to Top Plate using a 30mm clout. Do not fit 50mm nails at
this stage. Pre-drill holes to make nailing easier
(fig. 1)
.
Position Door Jamb Flashing and nail at the bottom. Posi-
tion right hand Door Jamb Flashing 903mm from left
hand Door Jamb Flashing
(cladding detail)
and nail in
place.
903mm
180mm
D008
CLADDING DETAIL
Birds Eye View