103.4  Electronics Cabinet Voltage Check

Using a voltmeter, check for correct nominal battery voltage between battery NEG and POS wires. Voltage reading 
should be 24 VDC ±10% of system DC voltage. 

CAUTION:

 Ensure all connections are fully engaged. Failure to do so may create an unsafe condition or fire hazard.

104.  Final Installation Checklist

104.1  Pre-Start-Up Systems Check

Complete the following:

•  Ensure the LiteGear Inverter cabinet is securely fastened to a wall or other structure.
•  Ensure that the input circuit breaker in the building service panel serving as the AC supply to the LiteGear 

 

  system is in the OFF position. 

•  Check for proper ground connections in the LiteGear cabinet, the building service panel, and the external load

 

  distribution panel. 

•  Check for any loose wiring connections in the LiteGear cabinet, the building service panel, and the external load 

 

  distribution panel. 

•  Check that correct nominal battery voltage (24 VDC) is present in the LiteGear cabinet between the battery NEG

 

  and POS wires.  

•  Securely fasten cover and ensure no wires are pinched.

105.  System Start-Up Procedure

105.1  Sequence of Steps 

The LiteGear inverter system is a sophisticated electronic backup power supply. Care must be taken to follow the 
steps below in their exact sequence. Failure to do so can result in possible equipment damage or failure. 

105.2  Start-Up Procedure Steps

CAUTION:

 Familiarize yourself with the shut down procedure (section 300.1) before proceeding. 

•  Make sure the cover is installed and secured. 
•  At the building service panel, energize the circuit breaker serving as the AC supply disconnect to the LiteGear 

system. 

•  The system should turn “ON”; the green “AC-ON” LED will illuminate. 

106.  System Verification

106.1  Initial System Status

The connected load should be energized and the “AC ON” LED should be illuminated (green). Allow a minimum 

24-hour charge period before testing the inverter system. If you need assistance, call Dual-Lite’s Technical Support 
Center at 1-800-848-6439. 

106.2  System Transfer Test

Press the momentary “TEST” switch or, for a prolonged discharge test, de-energize the service panel circuit breaker 

serving as AC input circuit breaker. The unit will transfer to inverter mode, the "AC On" LED will extinguish and the 
"Inverter ON" LED will illuminate (amber). All connected loads should be energized. 

Allow the inverter to run for several minutes or until satisfied with its operation. Energize the service panel breaker to 

end the prolonged discharge test and return the unit to standby mode. 

Summary of Contents for LiteGear

Page 1: ...Installation Instructions and User Manual 250 VA Inverter Power System...

Page 2: ...Battery acid can cause burns to skin and eyes If acid is spilled on skin or in the eyes flush with fresh water and contact a physician immediately 6 Equipment should be mounted in locations where it...

Page 3: ...rocedure 9 105 1 Sequence of Steps 9 105 2 Start Up Procedure Steps 9 106 System Verification 9 106 1 Initial System Status 9 106 2 System Transfer Test 9 200 Status Indicators 10 200 1 Indicators Pro...

Page 4: ...ill filings may damage the unit and prevent it from operating If additional or larger entry points are needed use a chassis punch to enlarge the appropriate knockout Do not add unnecessary knockouts R...

Page 5: ...eGear inverter system unit the unit can supply power from the AC line or from its batteries To avoid equipment damage or personal injury always assume that there is voltage inside the LiteGear inverte...

Page 6: ...s product with normally off lighting loads requires rewiring the circuit board to bypass an internal relay This process should only be performed by qualified personnel Refer to Fig 101 2 For 120VAC Op...

Page 7: ...tal wristwatches or other metal objects and jewelry Don t carry metal objects in pockets where the objects can fall onto the batteries or into the LiteGear inverter system Tools must have insulated ha...

Page 8: ...the red wire from the electronic module to the Positive Terminal of battery 1 and connect the blue wire to the Negative Terminal of battery 2 CAUTION Be careful to follow the bolt orientation shown i...

Page 9: ...sophisticated electronic backup power supply Care must be taken to follow the steps below in their exact sequence Failure to do so can result in possible equipment damage or failure 105 2 Start Up Pr...

Page 10: ...essing the test switch LED Status Indicator bi color green red LED Green Status Indicator During normal operation the green status LED will be constantly illuminated indicating the presence of AC powe...

Page 11: ...rt Code Faults Battery not connected battery string wiring is incomplete battery fuse FUSE1 on inverter pcb open Battery fault battery voltage below 24V following one minute test battery voltage below...

Page 12: ...unit After disconnecting the unit from the AC supply allow at least 5 minutes for capacitors to discharge before attempting service procedures If the service technician does not need to access the in...

Page 13: ...contain corrosive acids or caustic alkalis and toxic materials and can rupture or leak if mistreated Remove rings and metal wristwatches or other metal objects and jewelry Don t carry metal objects in...

Page 14: ...dispose of batteries in a fire the batteries could explode Do not open or mutilate batteries Released electrolyte is highly toxic and harmful to the skin and eyes CAUTION Batteries contain lead Many s...

Page 15: ...15 Notes...

Page 16: ...Hubbell Lighting Inc brand with representatives offices in principal cities throughout North America Copyright Hubbell Lighitng Inc All Rights Reserved Specifications subject to change without notice...

Reviews: