65
ED50
01-2020
DL4615-001
dormakaba ED50 Installation Instructions – Fine cover
Chapter 19
19.1 First commissioning
Fig. 19.1.2 Power switch
Fig. 19.1.1 Program switch
2
Power switch
Fig. 19.1.3 4 button keypad,
2 digit display
3
Four button
keypad
4
Two digit display
19 Single door first commissioning
1
Program switch,
3 position
o
2
4
3
> 3s Reset
< 3s Quit
> 3s
PRG
< 3s
LEARN
Fact-Setup
> 3s
> 8s
Conditions prior to commissioning.
1. ED50 operator is installed.
2. Standard push arm or arm with track is installed.
3. Key switches and other separately supplied
hardware are installed and connected to operator.
4. 115 Vac branch circuit to operator is energized.
5. Operator motor is cold.
CAUTION
Motor must be cold for commissioning!
Step 1
Program switch to CLOSE position.
Step 2
Power switch to ON position.
System check.
• Series of letters and numbers
rapidly displayed.
Control unit self check.
• Two segments jumping back
and forth.
Horizontal dashes move up and
down.
Step 3
Press 4 button keypad
down button
.
While 2 digit display segments
move up and down, letters and
numbers will change if required
to display correct orientation.
Display scrolls:
• Device ID (Ed 50)
• Firmware version
(format F x x x x)
Program mode display.
Program mode will be displayed
indicating system requires further
parameter settings.
TIPS AND RECOMMENDATIONS
If pressing down button (Step 3) does not
result in desired display orientation,
return to Step 2, turn power button off, then
on to repeat commissioning steps.
19.1.1 First commissioning.