Installation, Operation and Maintenance manual

25

PowerCore

®

 Dust Collectors  - Series CPC

Six-monthly
The fan impellor has been dynamically balanced and the fan assembly vibration level 

should be in line with category BV-3, ISO 14694.  An assessment of vibration should 

be made every six months, or after a significant emission, or after any misuse and a 

record kept of measured values.  Excessive vibration levels should be investigated 

and corrected immediately.

  Vibration monitoring is mandatory on category 2G, 3G and 2D fan assemblies.

Annually
1.  Moisture separator – Isolate the compressed air supply;  remove and clean the 

filter element.

2.  Air manifold – Having isolated the compressed air supply, remove the drain plug 

and air inlet connections and clean out any accumulated sludge and inspect to 

any current local legislation.

  It may be necessary to remove a diaphragm valve for internal inspection 

purposes.

3.  Doors  –  Check the dust seals on all access doors for damage or ageing and 

ensure that they are properly seated to prevent entry of water.  This is particularly 

important where the collector is located outside or in a wet atmosphere.

  Faulty seals must be replaced.

4.  Flameproof maintenance – It is important that all flameproof enclosures, motors 

and cable glands are inspected for corrosion and tightness on an annual basis.

 In particularly aggressive environments, this period should be more 

frequent.

5.  Antistatic earthing (if fitted) – Check collector earthing continuity.
6.  Explosion risks – Check measures taken to avoid ignition sources are still in place.
7.  Fan maintenance – Open access door(s) and, by looking through fan inlet eye, 

inspect fan thoroughly. If necessary, remove all residual dust accumulation.  

(Although the fan is located on the clean side of the collector, it is possible for 

low quantities of dust to migrate through the filter media).

  The fan should be inspected immediately after any period of significant 

dust emission, i.e. due to damaged filter media or seal etc.

  The fan should be inspected immediately if there is any unexpected noise, 

temperature or vibration.

  The fan should be inspected every twelve months or immediately following 

any misuse.

  If inspection reveals any damage then the fan must not be put back into 

service until properly repaired or replaced.

Summary of Contents for PowerCore CPV-6F

Page 1: ...PowerCore Mist Collectors Series CPC INSTALLATION OPERATION AND MAINTENANCE MANUAL Publication 1A65198039 3023J 1019 MASTER LANGUAGE ENGLISH...

Page 2: ...rs with integral fan 14 Overload protection 14 Control of ancillary equipment and interlocks 14 EEx controls 15 Antistatic earthing 15 Explosion relief 16 Installation check list 17 COMMISSIONING 18 I...

Page 3: ...sembly 11 Figure 5 Earthing connection between collector side panel and hopper CPC 6 illustrated 13 Figure 6 Attaching Power Box to collector CPC 6 illustrated 14 Figure 7 Explosion relief detection d...

Page 4: ...ectrical installation inspection and maintenance work Pneumatic installation inspection and maintenance work Any access to internal classified potentially explosive atmospheres where there may be a ri...

Page 5: ...o thermal protection devices to prevent them exceeding their maximum surface temperature All electrical equipment should comply with a category according to EN 60079 0 Where the dust being processed c...

Page 6: ...he basis of safety is based on using a conductive bin dusts with a median particle size of less than 400 m and advising frequent emptying You may wish to consider the use of a sprinkler system when ha...

Page 7: ...agm valve 8 Compressed air distribution manifold 9 Compressed air inlet 10 Filter pack retainer 11 Filter pack 12 Explosion relief 13 Discharge hopper 14 Support 15 Dust container 1 6 7 8 9 10 11 12 1...

Page 8: ...vices All ducts piping or electrical services must be adequately supported All external equipment connected to the outlet e g ducting should be correctly sealed This can be achieved by applying a cont...

Page 9: ...dation fixing positions are provided in Publication 3021 Foundation bolts are not supplied by Donaldson 4 Tighten foundation bolts legs and cross bracing 5 Stand hopper on the discharge end and apply...

Page 10: ...djust height to provide an effective seal between dust container and sealer gear When the collector is fitted with an earthing post an earthing connection must be made between the base panel and the d...

Page 11: ...bracing to legs using hardware supplied Do not tighten hardware at this stage All bracing require fitting 2 Lift support assembly into required position and ensure assembly is level 3 Drill through b...

Page 12: ...ssed air requirements PowerCore dust collectors require an independent supply of clean dry oil free compressed air Details of atmospheric pressure and quantity are given in Table 5 refer to Specificat...

Page 13: ...992 to provide adequate isolation and emergency stop facilities Due to the varied nature of site installations this cannot be provided by Donaldson but instead is the responsibility of the customer Al...

Page 14: ...ble 6 refer to Specification section Overload protection All feeder circuits should be adequately protected with suitably rated fuses and contactors with integral overload protection Control of ancill...

Page 15: ...ollowing control systems EExd solenoids and remote controller When this option is fitted the dust collector has its solenoid valves in an EExd IIb T6 enclosure mounted on to the collector body A contr...

Page 16: ...event of an explosion the signal should be taken from the explosion relief panel detection device refer to figure 8 If the collector is fitted with a Power Box the signal may be connected to the inpu...

Page 17: ...n check list Ensure the dust collector is securely bolted to the support structure Ensure the support structure is securely bolted to the floor Ensure compressed air supply is installed correctly and...

Page 18: ...c power is available Ensure the compressed air manifold has sufficient protection for over pressure Start the compressor and check the air supply is maintained at the recommended pressure If applicabl...

Page 19: ...will ensure that a PowerCore dust collector installation is maintained at optimum efficiency On installations where the inlet duct is relatively short this procedure may result in a dust emission occu...

Page 20: ...tion continuous b Cleaning operation intermittent each filter pack is cleaned separately in turn 1 Cleaned air outlet 2 Fan 3 Filter pack 4 Contaminated air inlet 5 Diaphragm valve 6 Compressed air ma...

Page 21: ...taken to ensure that dust spillage is kept to a minimum to avoid the creation of potentially explosive atmospheres and secondary hazards Dust containers should be securely replaced and resealed prior...

Page 22: ...work must be carried out by competent personnel These risks include inhalation of dust and potential explosion hazards Appropriate personal protection equipment PPE should be used e g dust mask safet...

Page 23: ...accumulated dust before putting the collector into operation Filter pack resistance can be checked by connecting a U tube manometer or differential type pressure gauge to tapping points on the collect...

Page 24: ...following procedure see figure 11 Use service kit available from Donaldson 1 Remove nylon tube A by pulling out from valve 2 Remove the hexagon head set screws and shakeproof washers securing the val...

Page 25: ...ter This is particularly important where the collector is located outside or in a wet atmosphere Faulty seals must be replaced 4 Flameproof maintenance It is important that all flameproof enclosures m...

Page 26: ...g fasteners Swing door fully open and engage door locking mechanism 4 Release filter pack retainer wing nuts and washers Remove filter pack retainers 5 Remove each filter pack by lifting straight up 6...

Page 27: ...ove side access cover 4 Remove fan assembly securing bolts from inside clean air chamber 5 The fan assembly can now be removed using a suitable lifting arrangement Fan assembly weights K5 K7 SF40 K10...

Page 28: ...acer onto motor shaft 14 Align keyway of impeller hub onto key and slide impeller onto motor shaft 15 Replace hub retaining washer and shakeproof washer Apply thread lock to motor end shaft bolt and r...

Page 29: ...top panel apply 5 mm bead of sealing compound along each side of fixing holes 7 Replace side access cover Before replacing side access cover apply 5 mm bead of sealing compound along each side of fixi...

Page 30: ...tions For Star Delta applications check motor is in Delta Incorrect fan motor rotation Check electrical connections and transpose if necessary Insufficient airflow Fan motor stopped Check motor supply...

Page 31: ...ial used for manifold construction Structural hollow section Minimum metal thickness before manifold requires special inspection To improve corrosion resistance the manifold is painted externally and...

Page 32: ...50 Hz IEC 60034 30 kW Nameplate details Range 0 75 1 5 230 3 50 D 220 240 D 400 3 50 Y 380 420 Y 2 2 and above 400 3 50 D 380 420 D 690 3 50 Y 660 690 Y 3 Phase 60 Hz kW Nameplate details Range 0 75...

Page 33: ...3 Fan motor K15 fan 11 0 kW IP55 380 420V 660 690V 50 Hz 1A 2757 3280 3 Fan motor ART 562 fan 11 0 kW IP55 380 420V 660 690V 50 Hz Consult Donaldson 4 K5 fan assembly including motor 1A 3321 9208 4 K7...

Page 34: ...Controller and Publication 262 3143 for TCB Compressed air assembly 10 Diaphragm valve 1A 3189 9011 11 Diaphragm valve service kit item not illustrated 1A 2565 3204 12 Gasket diaphragm valve item not...

Reviews: