background image

Installation, Operation and Maintenance manual

18

PowerCore

®

 Dust Collectors  - Series CPC

COMMISSIONING

  It is a requirement of the Supply of Machinery (Safety) Regulations 1992 to 

provide adequate isolation and emergency stop facilities.  Due to the varied 

nature of site installations this cannot be provided by Donaldson but instead 

is the responsibility of the customer.

Installation check list

Ensure the dust collector is securely bolted to the support structure.

Ensure the support structure is securely bolted to the floor.

Ensure all ducting is complete and all detachable panels are in position.

Ensure collectors fitted with an earthing post are suitably earthed.

Where fitted, ensure explosion relief panels are venting to a safe area.

Open the access door(s) and ensure the seal is intact, then close and secure 

the door(s).

Ensure controller is connected to the correct voltage and the pulse interval and  

duration settings are correct.  For 24V DC ensure polarity is correct.  It is essential 

that the controller is earthed for both AC and DC connections.

Ensure electric power is available.

Ensure the compressed air manifold has sufficient protection for over-pressure.

Start the compressor and check the air supply is maintained at the recommended 

pressure.

If applicable, start up the discharge equipment (e.g. screw conveyor, rotary valve, 

belt feeders etc.).

Switch on the controller and check that all valves operate in sequence (listen for 

exhaust pulses).  As each valve operates, the air pressure reading should drop 

to approximately 50% of the initial setting and then return to the initial value.

If fitted, start up the main fan and check for correct rotation and the full load 

current is not exceeded (refer to fan rotation label located on rear panel of fan 

section).

Verify operation of the interlocks and audible warning system if fitted.

If any of the above check boxes are not ticked, then the reasons why should be 

investigated.  (Refer to fault location table in ‘Maintenance’ section).

Start-up sequence

Having completed all the necessary checks, the equipment may be put into operation.  

A typical installation, as shown in figure 7, should be started up as follows:
1.  Start up compressed air supply.
2.  Set the equipment being served, if applicable, in motion.
3.  Switch on discharge equipment (if applicable).
4.  Switch on controller.
5.  Start main fan.

Summary of Contents for PowerCore CPV-6F

Page 1: ...PowerCore Mist Collectors Series CPC INSTALLATION OPERATION AND MAINTENANCE MANUAL Publication 1A65198039 3023J 1019 MASTER LANGUAGE ENGLISH...

Page 2: ...rs with integral fan 14 Overload protection 14 Control of ancillary equipment and interlocks 14 EEx controls 15 Antistatic earthing 15 Explosion relief 16 Installation check list 17 COMMISSIONING 18 I...

Page 3: ...sembly 11 Figure 5 Earthing connection between collector side panel and hopper CPC 6 illustrated 13 Figure 6 Attaching Power Box to collector CPC 6 illustrated 14 Figure 7 Explosion relief detection d...

Page 4: ...ectrical installation inspection and maintenance work Pneumatic installation inspection and maintenance work Any access to internal classified potentially explosive atmospheres where there may be a ri...

Page 5: ...o thermal protection devices to prevent them exceeding their maximum surface temperature All electrical equipment should comply with a category according to EN 60079 0 Where the dust being processed c...

Page 6: ...he basis of safety is based on using a conductive bin dusts with a median particle size of less than 400 m and advising frequent emptying You may wish to consider the use of a sprinkler system when ha...

Page 7: ...agm valve 8 Compressed air distribution manifold 9 Compressed air inlet 10 Filter pack retainer 11 Filter pack 12 Explosion relief 13 Discharge hopper 14 Support 15 Dust container 1 6 7 8 9 10 11 12 1...

Page 8: ...vices All ducts piping or electrical services must be adequately supported All external equipment connected to the outlet e g ducting should be correctly sealed This can be achieved by applying a cont...

Page 9: ...dation fixing positions are provided in Publication 3021 Foundation bolts are not supplied by Donaldson 4 Tighten foundation bolts legs and cross bracing 5 Stand hopper on the discharge end and apply...

Page 10: ...djust height to provide an effective seal between dust container and sealer gear When the collector is fitted with an earthing post an earthing connection must be made between the base panel and the d...

Page 11: ...bracing to legs using hardware supplied Do not tighten hardware at this stage All bracing require fitting 2 Lift support assembly into required position and ensure assembly is level 3 Drill through b...

Page 12: ...ssed air requirements PowerCore dust collectors require an independent supply of clean dry oil free compressed air Details of atmospheric pressure and quantity are given in Table 5 refer to Specificat...

Page 13: ...992 to provide adequate isolation and emergency stop facilities Due to the varied nature of site installations this cannot be provided by Donaldson but instead is the responsibility of the customer Al...

Page 14: ...ble 6 refer to Specification section Overload protection All feeder circuits should be adequately protected with suitably rated fuses and contactors with integral overload protection Control of ancill...

Page 15: ...ollowing control systems EExd solenoids and remote controller When this option is fitted the dust collector has its solenoid valves in an EExd IIb T6 enclosure mounted on to the collector body A contr...

Page 16: ...event of an explosion the signal should be taken from the explosion relief panel detection device refer to figure 8 If the collector is fitted with a Power Box the signal may be connected to the inpu...

Page 17: ...n check list Ensure the dust collector is securely bolted to the support structure Ensure the support structure is securely bolted to the floor Ensure compressed air supply is installed correctly and...

Page 18: ...c power is available Ensure the compressed air manifold has sufficient protection for over pressure Start the compressor and check the air supply is maintained at the recommended pressure If applicabl...

Page 19: ...will ensure that a PowerCore dust collector installation is maintained at optimum efficiency On installations where the inlet duct is relatively short this procedure may result in a dust emission occu...

Page 20: ...tion continuous b Cleaning operation intermittent each filter pack is cleaned separately in turn 1 Cleaned air outlet 2 Fan 3 Filter pack 4 Contaminated air inlet 5 Diaphragm valve 6 Compressed air ma...

Page 21: ...taken to ensure that dust spillage is kept to a minimum to avoid the creation of potentially explosive atmospheres and secondary hazards Dust containers should be securely replaced and resealed prior...

Page 22: ...work must be carried out by competent personnel These risks include inhalation of dust and potential explosion hazards Appropriate personal protection equipment PPE should be used e g dust mask safet...

Page 23: ...accumulated dust before putting the collector into operation Filter pack resistance can be checked by connecting a U tube manometer or differential type pressure gauge to tapping points on the collect...

Page 24: ...following procedure see figure 11 Use service kit available from Donaldson 1 Remove nylon tube A by pulling out from valve 2 Remove the hexagon head set screws and shakeproof washers securing the val...

Page 25: ...ter This is particularly important where the collector is located outside or in a wet atmosphere Faulty seals must be replaced 4 Flameproof maintenance It is important that all flameproof enclosures m...

Page 26: ...g fasteners Swing door fully open and engage door locking mechanism 4 Release filter pack retainer wing nuts and washers Remove filter pack retainers 5 Remove each filter pack by lifting straight up 6...

Page 27: ...ove side access cover 4 Remove fan assembly securing bolts from inside clean air chamber 5 The fan assembly can now be removed using a suitable lifting arrangement Fan assembly weights K5 K7 SF40 K10...

Page 28: ...acer onto motor shaft 14 Align keyway of impeller hub onto key and slide impeller onto motor shaft 15 Replace hub retaining washer and shakeproof washer Apply thread lock to motor end shaft bolt and r...

Page 29: ...top panel apply 5 mm bead of sealing compound along each side of fixing holes 7 Replace side access cover Before replacing side access cover apply 5 mm bead of sealing compound along each side of fixi...

Page 30: ...tions For Star Delta applications check motor is in Delta Incorrect fan motor rotation Check electrical connections and transpose if necessary Insufficient airflow Fan motor stopped Check motor supply...

Page 31: ...ial used for manifold construction Structural hollow section Minimum metal thickness before manifold requires special inspection To improve corrosion resistance the manifold is painted externally and...

Page 32: ...50 Hz IEC 60034 30 kW Nameplate details Range 0 75 1 5 230 3 50 D 220 240 D 400 3 50 Y 380 420 Y 2 2 and above 400 3 50 D 380 420 D 690 3 50 Y 660 690 Y 3 Phase 60 Hz kW Nameplate details Range 0 75...

Page 33: ...3 Fan motor K15 fan 11 0 kW IP55 380 420V 660 690V 50 Hz 1A 2757 3280 3 Fan motor ART 562 fan 11 0 kW IP55 380 420V 660 690V 50 Hz Consult Donaldson 4 K5 fan assembly including motor 1A 3321 9208 4 K7...

Page 34: ...Controller and Publication 262 3143 for TCB Compressed air assembly 10 Diaphragm valve 1A 3189 9011 11 Diaphragm valve service kit item not illustrated 1A 2565 3204 12 Gasket diaphragm valve item not...

Reviews: