Downflo Oval, DFO 2-4 and 3-6
6
Do Not lift with
this orientation
angle not to
exceed 30°
from vertical
(min 60°
from horizontal)
1. Lift cabinet.
2. Apply sealant to hopper flange.
3. Fasten hopper to cabinet.
4. Assemble legs and cross braces.
5. Lift unit and hopper into position
over legs and lower slowly.
6. Fasten legs to unit securely.
7. Lift assembled unit to location.
8. Support and level unit.
9. Tighten all fasteners.
10. Remove crane.
Typical Installation
Typical Installation
Summary of Contents for DFO 2-4
Page 1: ...2...
Page 3: ......
Page 5: ......
Page 12: ......
Page 14: ......
Page 15: ......
Page 17: ...Downflo Oval DFO 2 4 and 3 6 14 This Page Intentionally Left Blank...
Page 19: ......
Page 21: ...Downflo Oval DFO 2 4 and 3 6 18 This Page Intentionally Left Blank...
Page 22: ......
Page 23: ......
Page 24: ......
Page 30: ......
Page 37: ......
Page 41: ...Downflo Oval DFO 2 4 and 3 6 38 Service Notes Date Service Performed Notes...
Page 42: ...39 Donaldson Company Inc Service Notes Date Service Performed Notes...
Page 43: ......