3. Setting Up and Running a Test
72A-2570-01 Rev. K 07/2011
3-15
Step 4: Select and Run a Test
By running the shorted-lead test, you have already followed the complete
procedure for running a test. This section provides a testing procedure for a
transformer that has already been set up in SFRA and associated with a test
template.
Requirements for This Test
Complete these actions before you run a test:
1.
Perform the shorted-lead test.
Do not omit it.
To run the test, go to
1: Set Up and Run a Shorted-lead Test” on page 3-2
.
2.
Set up the transformer in SFRA. To do this, go to
into the SFRA Database” on page 5-5
3.
Ground the transformer. Do not omit this procedure. If you have not
already done so, go to
“Step 2: Ground the Transformer” on page 3-12
.
4.
Prepare the transformer for testing. If you have not already done so, go to
“Step 3: Prepare the Transformer for Testing” on page 3-14
.
Associate the Transformer with a Test Template
A transformer must be associated with a test template before it can be tested.
To do this:
1.
In the main window of the SFRA software, open the
Edit
menu and select
Edit Apparatus
(
).
Figure 3.24 Edit Apparatus Option on Edit Menu
The Test Equipment Editor window opens (
).
Summary of Contents for SFRA
Page 12: ...Sweep Frequency Response Analyzer SFRA User Guide xii 72A 2570 01 Rev K 07 2011...
Page 14: ...Sweep Frequency Response Analyzer SFRA User Guide xiv 72A 2570 01 Rev K 07 2011...
Page 24: ...Sweep Frequency Response Analyzer SFRA User Guide 2 4 72A 2570 01 Rev K 07 2011...
Page 56: ...Sweep Frequency Response Analyzer SFRA User Guide 3 32 72A 2570 01 Rev K 07 2011...
Page 78: ...Sweep Frequency Response Analyzer SFRA User Guide 5 18 72A 2570 01 Rev K 07 2011...
Page 98: ...Sweep Frequency Response Analyzer SFRA User Guide A 20 72A 2570 01 Rev K 07 2011...
Page 110: ...Sweep Frequency Response Analyzer SFRA User Guide C 6 72A 2570 01 Rev K 07 2011...
Page 116: ...Sweep Frequency Response Analyzer SFRA User Guide D 6 72A 2570 01 Rev K 07 2011...