Adjust the base leveling knob (5) located in the
base (6) to stabilize the tool when necessary.
•
Adjust the head (8) for a level or plumb application.
Wall set-up (fig. C2 - C5)
The tool has been equipped with a wall mount (11) for
mounting to wall track to aid in drop ceiling installation
and other specialty leveling projects (fig. C2).
•
Turn the tool on its side with the battery pack
(15) below and the wall mount clamp (11) in
position for attachment to the wall track (fig. C3).
•
With the base (6) facing the wall, turn the wall
mount clamping lock (12) in the clockwise
direction to open the clamp jaws.
•
Place the clamp jaws around the wall track and
turn the wall mount clamping lock (12) in the anti-
clockwise direction to close the clamp jaws shut
on the track.
•
Ensure that the wall mount clamping lock (12) is
securely locked.
Before attaching the tool to a wall track
ensure that the track is properly secured
to the wall.
•
Alternatively, the tool can be hung on the wall
using the mounting holes (24) in the base (fig. C2).
- Hold the tool at the desired position against the
wall and mark the location of the two mounting
holes on the wall (fig. C4).
- Drill a hole at each of the marked locations
(required: ø 6 mm, approx. 35 mm deep).
- Insert a corresponding plug into each of the holes.
- Turn a screw into each of the plugs
(required: 6 x 50 mm).
- Hang the tool on the screws.
•
Adjust the base leveling knob (5) located in the
base (6) to stabilize the tool when necessary.
•
Adjust the head (8) for a level application.
Tripod set-up (fig. C5)
The tool has been equipped with a tripod receptacle
for mounting to the DE0736 tripod (optional) or any
other tripod with the required ratings stated in the
technical data.
•
Place the tripod (25) on a relatively smooth and
level surface.
•
Mount the tool to the tripod by turning the threaded
pin (26) into the receptacle (27) in the base.
•
Adjust the head (8) for a level or plumb application.
Adjusting the tool (fig. D1 - D5)
The laser head (8) can be pivoted to adjust the tool for
both level (fig. D1) and plumb (fig. D2) applications.
Level adjustment (fig. D1, D3 & D4)
•
Release the head position lever (14) and pivot the
head (8) into leveling position as shown:
- The correct leveling position for the head with
the tool in a floor or tripod set-up is shown in
fig. D1.
- The correct leveling position for the head with
the tool in a wall set-up is shown in fig. D3.
•
Re-tighten the lever.
•
Read the air levels (9 & 18) to check whether the
head is level (fig. D4).
•
If adjustment is required, proceed as follows:
•
Turn the level adjustment knobs (10 & 17) until
the head is level.
Plumb adjustment (fig. D2 & D5)
A plumb orientation is performed with the tool in a
floor or tripod set-up.
•
Release the head position lever (14) and pivot the
head (8) into plumbing position as shown (fig. D2).
Re-tighten the lever.
•
Read the air level (28) to check whether the head
is level (fig. D5).
•
If adjustment is required, proceed as follows:
•
Turn the level adjustment knob (29) until the head
is level.
Aligning the laser line (fig. E1 & E4)
Level alignment
•
With the tool switched on and the laser head
rotating, align the laser line with the position mark.
•
If adjustment is required, proceed as follows:
With tool in floor set-up (fig. E1):
•
The tool can be placed on any sturdy object to
obtain the required height.
With tool in wall set-up (fig. E2):
•
Loosen the locking knob (16) and adjust the rack
pinion wheel (13) to set the tool to the correct
position. Tighten the locking knob (16).
E N G L I S H
en - 6
26
Summary of Contents for DW073
Page 1: ... DW073 ...
Page 3: ...A 7 8 9 10 11 15 14 12 13 3 4 5 6 1 2 16 17 18 19 15 21 20 ...
Page 4: ...22 19 15 23 A B B1 B2 B3 ...
Page 5: ...8 5 6 C1 12 24 11 11 8 12 15 5 6 C2 C3 ...
Page 6: ...5 8 6 C4 25 8 26 27 C5 8 14 D1 D2 8 14 ...
Page 7: ...8 14 9 17 10 18 D3 D4 29 28 D5 ...
Page 8: ...E1 13 E2 ...
Page 9: ...13 30 E3 E4 ...
Page 10: ...1 F 7 8 G 1 3 29 2 28 H I1 I2 ...
Page 141: ......
Page 142: ......